HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
J AND K INTEGRATED TEXTILE PARK LIMITED TH RAM AVTAR AGGARWAL – Appellant
Versus
UNION OF INDIA TH ITS SECRETARY MINISTRY OF TEXTILE AND OTHERS – Respondent
WP(C) 606/2021
['ARUN DEV SINGH', '', 'PRANAV KOHLI', 'SR ADV', 'VISHAL SHARMA ASGI']
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on : 19.09.2022
Pronounced on : 14.10.2022
WP(C) No. 606/2021 (O&M)
J&K Integrated Textile Park Limited
…..Appellant(s)/Petitioner(s)
Through: Mr. Pranav Kohli, Sr. Advocate with
Mr. Arun Dev Singh, Advocate
Vs
Union of India and ors.
.…. Respondent(s)
Through: Mr. Vishal Sharma, DSGI
Mr. Parveen Kapahi, Advocate
Ms. Monika Koihli, Advocate
Coram: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
HOB’BLE MR. JUSTICE RAJESH SEKHRI, JUDGE
JUDGMENT
Per Oswal-J
1.
In the present writ petition, the petitioner has sought for the following
reliefs:
i.) Certiorari seeking quashment of the e-auction Notice dated 13.02.2021
and 06th March, 2021, by virtue of which e-auction is scheduled on 25th and
30th March, 2021 to the extent of factory and buildings owned by the
petitioner SPV.
ii) Prohibition restraining the respondent No. 3-Bank from proceeding
further with the impugned e-auction notices dated 13.02.2021 and
06.03.2021, by virtue of which e-auction is scheduled on 25th and 30th
March, 2021 in any manner.
2 WP(C) No. 606/2021
iii) Mandamus commanding upon the respondents to delete and exclude the
factory and buildings owned by the petitioner SPV from the e-auction
notices dated 13.02.2021 and 06.03.2021.
iv) Mandamus commanding upon the respondent No. 3-Bank to de-seal the
factory and consequently release the actual physical possession of the
factory and buildings of the petitioner SPV.
2.
The case projected by the petitioner in this writ petition is that petitioner-
J&K integrated Textile Park Limited, is a Company incorporated under the
Companies Act on 15th March 2009 and the main object of the petitioner-
company is to act as a Special Purpose Vehicle for implementing different
schemes of the Central/State Governments. The petitioner pursuant to the
Scheme for Integrated Textile Park (SITP) floated by the respondent No. 1,
made a proposal for establishment of Textile Park Project and that was
approved by the respondent No. 1, initially with project cost Rs. 47.11 crores.
Subsequently, the project cost was changed to Rs. 44.11 crores. The
Government of India grant for project was changed from Rs. 40.00 to Rs.
39.70 crores. As per Clause 2.4 of the Scheme (supra), the total project cost
for the purpose of the scheme includes cost on account of ITP components as
listed under Groups B, C & D provided the ownership of the factory and
buildings vests with the Special Purpose Vehicle. The land, that formed
component A of Scheme, was not included in the total project cost.
3.
The petitioner was allotted 200 kanals of land at Industrial Estate Govindsar,
Kathua. The lease deed dated 22.03.2012 came to be executed between the
respondent No. 2 and the petitioner for a period of 90 years. Thereafter,
Memorandum of Agreement dated 29th May, 2013 also came to be executed
between the petitioner and respondent No. 1.
3 WP(C) No. 606/2021
4.
The petitioner in turn claims to have executed Lease Agreement with the nine
units holders, namely, J and K Textorium Pvt. Ltd, Green Textorium Pvt.
Ltd., J and K Synthetic Pvt. Ltd., Silklon Synthetic Pvt. Ltd., Toplon
Industries Pvt. Ltd, Natural Industries, Orbit Spinning Pvt. Ltd., Jyotsna
Industries Pvt. Ltd. and Silklon Processors Pvt. Ltd. The petitioner has placed
on record Lease Agreement dated 28th December, 2013 executed between the
petitioner and Toplon Industries Pvt. Ltd. i.e. respondent No. 8. It needs to be
noted that the lease agreements executed with other unit holders have not
been placed on record. As per the lease agreement dated 28th December 2013,
the lessee units cannot claim any ownership on the demis