HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
PIR PANCHAL COMPANY PVT.LTD – Appellant
Versus
UOI.TH.MINISTRY OF RAILWAYS AND ORS – Respondent
AA 20/2013
HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
AA no. 20/2013
Date of order: 28.03.2014
Pir Panchal Company Pvt. Ltd. v. Union of India and ors
Coram:
Hon’ble Mr. Justice M. M. Kumar, Chief Justice
Appearing counsel:
For the Petitioner(s) : Mr. Himanshu Beotra, Advocate.
For the Respondent(s) : Mr. P. S. Chandel, CGSC.
i)
Whether to be reported in
Press, Journal/Media
:
Yes
ii/
Whether to be reported in
Digest/ Journal
:
Yes
M. M. Kumar, CJ
1.
The petitioner Pir Panchal Company Pvt. Ltd. has
approached this Court with a prayer for appointment of an
independent arbitrator under Section 11 of the Jammu and
Kashmir Arbitration and Conciliation Act, 1997.
2.
Few facts may first be set out to put the controversy in its
proper
perspective.
The
Deputy
Chief
Engineer,
Construction/Doubling Northern Railways issued NIT dated
28.09.2006 inviting tenders from eligible contractors for
construction
of
Railway
level/low
level
platform
at
Samba/Ghagwal and loading ramps at Samba block hut at
Basantar bridge, staff quarters and duty huts and lifting barrier
at level crossing between Jammu Ghagwal and other works
2
between
Vijaypur-Jammu-Ghagwal
in
connection
with
Jalandhar-Pathankot-Jammu Tawi doubling (Annexure A). The
petitioner was a successful tenderer. Accordingly acceptance
letter dated 02.08.2007 allotting the contract to the petitioner at
the rate of Rs. 2,20,00,244.67 was issued (Annexure B).
3.
The petitioner- company was directed to start the
execution of work vide letter 09.08.2007 (Annexure C). During
the execution of the work the petitioner-company was directed
to do some works in addition to the allotted work, which was
duly executed by it. According to the clauses of the contract
agreement it was provided that clear sites were available for
completion of various structures. A period of four months
commencing from 02.08.2007 was fixed. However, the
petitioner claims that on account of non-availability of clear sites
for execution of work there was delay in the execution which
was attributable to the respondents. The time therefore was
extended from time to time. It is appropriate to mention that
extensions were granted on many occasions and the work was
eventually completed in 49 months. It is alleged by the
petitioner that the total work on account of non-availability of the
site was reduced and in fact it resulted in financial losses to the
petitioner-company. Be that as it may, the work was completed
on 30.09.2011. In the Final Bill a large number of items of work
3
executed by the petitioner-company were not accounted for and
were found missing. The petitioner agitated and requested for
inclusion of the aforesaid items by letter dated 19.04.2012. A
sum of Rs. 7,37,36,975/- was claimed by the petitioner-
company. It is categorical case of the petitioner-company
pleaded in para no. 8 and 9, that there was pressure and undue
influence mounted on it to withdraw the claim made vide letter
dated 19.04.2012 and the petitioner was forced to agree for
release of undisputed amount of Rs. 20.74 lacs along with the
amount of performance bank guarantee, security deposit and
earnest money amounting to Rs. 25,13,904/-. It is positive case
of the petitioner that on account of undue influence, pressure
and threats the petitioner was forced to agree to accept the
undisputed amount by excluding the value of the additional
work executed. The respondents showed their inability to
process the final bill in presence of the claim made by the
petitioner in its letter dated 19.04.2012 because accepting such
a claim by respondents would have made the contract disputed
one which would cause disability to process the bill. Such a
course was considered contrary to t