UOI.TH.CHIEF ENGINEER,SAMPARK – Appellant
Versus
M/S D.KHOSLA AND CO – Respondent
CFA 18/2014
h475
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on :17.02.2022
Pronounced on : 09.05.2022
(through virtual mode)
Union of India
...Appellant(s)
Through:- Mr. Pranav Kohli, Sr. Advocate with
Mr. Rahul Sharma, Advocate
V/s
M/s D.Khosla and Company
...Respondent(s)
Through:-Mr. Sourabh Malhotra, Advocate
Coram: HON’BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
JUDGMENT
1.
Union of India through Chief Engineer (P) Sampark is in appeal
under Section 39 of J&K Arbitration Act, 2002 (1945 A.D.) [ <the Act=]
against the order and judgment of the Principal District Judge, Jammu [<the
Court below=] dated 11.01.2014 passed in File No.42/Award titled M/s D
Khosla and Company v. Chief Engineer (P) Sampark. The Court below
vide its judgment dated 11.01.2014, impugned in this appeal, has dismissed
the application of the Union of India filed under Section 30 and 33 of the
Act for setting aside the arbitral award dated 04.01.2008 passed by Brig
(Retd.) B.V.Ahuja, the sole arbitrator.
CFA No.18/2014
IA Nos.91/2014, 2/2015, 3/2015 &
1/2017
2 CFA No.18/2014
2.
Before adverting to the grounds of challenge pleaded and urged by
the appellant-Union of India to sustain challenge to the impugned order of
the Court below, it would be necessary to allude to the background facts
leading upto the filing of instant appeal.
Pursuant to an NIT issued by appellant for allotment of work of
<Design and Construction of Permanent Bridge Over River Niara Tawi at
65.51 on Akhnoor-Poonch Road in J&K State under Project Sampark= the
respondent-the contractor was found to be the successful bidder and
accordingly, a contract agreement was entered into between the Union of
India and the contractor on 14.06.1987. The lumpsum value of the contract
to be executed by the contractor was Rs.90,59,000/- with the completion
period of 24 months. The date of commencement of the work was stated as
8th August, 1988 and was to be completed and handed over by the
contractor by or before 7th August, 1990. It appears that on account of
certain delays and technical problems, the work could not be completed
within the stipulated period. On the request of the contractor, time to
complete the work in question was extended from time to time and as per
the last extension granted, the contractor was to complete the work by 31st
March, 1993. It appears that the contractor during the currency of the
contract approached the appellant for interim arbitration on the ground that
certain disputes between the parties were affecting both, progress of the
work and the payments. The Union of India did not oblige in the beginning
but later agreed to interim arbitration, which, however, did not materialize
thereafter. But, instead, the contract was terminated on 14.06.1993. Feeling
3 CFA No.18/2014
aggrieved by the termination of the contract agreement by the appellant, the
contractor approached the designated authority (Director General of Border
Roads) for appointment of an arbitrator under Clause-70 of the General
Conditions of the contract. The designated authority did not act on the
request of the contractor, which constrained him to approach the Court of
Principal District Judge, Jammu for appointment of an arbitrator in terms of
Clause 70 of the General Conditions of Contract to adjudicate upon the
disputes between the parties arising out of the contract. While the matter
was pending consideration of the Court below
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.