BENCH AT DHARWAD
EXECUTIVE ENGINEER (ELE.) – Appellant
Versus
SMT. PARVATEWWA W/O GOVINDAPPA GADAGI – Respondent
This appeal is filed by the defendant Nos.1 and 2
challenging the judgment and decree dated 19.02.2016
passed by the Principal Senior Civil Judge and CJM, Gadag,
whereby suit has been decreed. The defendant has been
directed to pay a sum of Rs.19,24,000/- with 6% interest.
The case of the plaintiff is that the plaintiff is
the owner of the land bearing Sy. No.237/2 of Dambal
village, Mundargi Taluk measuring 6 acres 19 guntas. It is
further case of the plaintiff that the said land is an
irrigated land, the plaintiff has invested huge amount of
Rs.15,00,000/- by availing the loan from the Bank. The
further case of the plaintiff that the plaintiff has grown
sugarcane on the said land. On 03.02.2011 at about 05:00
p.m. the fire has been broke out from the transformer
installed by the defendant. Due to that fire had caught to
the standing crop of sugarcane in the land belonging to
the plaintiff. The plaintiff suffered loss and claimed
- 3 -
damages of Rs.18,77,500/- for the sugarcane as well as
equipment and reparation.
3.
The further case of the plaintiff that on
05.02.2011, the adjacent property belonging to the
plaintiff’s son had also suffered damages due to catching
of fire
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.