HIGH COURT OF ORISSA
STATE OF ORISSA – Appellant
Versus
CH.NATABAR SAHOO – Respondent
ARBA 8/2002
['A S C', 'M/S S P MISHRA', '', 'S NANDA', 'S MISHRA', 'S DASH', 'S MISRA', 'M/S S MISHRA', 'B MOHANTY', 'R R JAISWAL', 'S K SAMANTARAY', 'A MOHAPATRA']
// 1 //
Page 1 of 7
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.8 of 2002
(Through hybrid mode)
State of Odisha and another
….
Appellants
-versus-
Choudhury Natbar Sahoo
(Dead) and others
….
Respondents
Advocates appeared in the case:
For Appellants:
- Mr. S. N. Das, Advocate
(Additional Standing Counsel)
For Respondent:
- Mr. S. P. Mishra, Senior Advocate
CORAM:
JUSTICE ARINDAM SINHA
JUDGMENT
13.10.2022
1.
Mr. Das, learned advocate, Additional Standing Counsel
appears on behalf of appellant. He submits, the award was made under
provisions in Arbitration Act, 1940. State had challenged the award
under section 33, contending that there was misconduct, as defined in
section 30. The Court below erred in not appreciating contentions
made before it and hence, the appeal.
2.
He submits, the only point for adjudication of the appeal is that
// 2 //
Page 2 of 7
the tribunal applied 1972 schedule of rates in respect of 2nd Running
Account (RA) to final bills. He submits, the contract was made on 1st
May, 1972. Pursuant to respondent having submitted tender on 21st
July, 1971 per the 1964 schedule of rates. Work order was issued on
26th April, 1972. The work was abandoned and the contract closed on
6th July, 1974. Respondent raised and obtained payments till 9th RA bill
as on 12th July, 1974. In the circumstances, respondent having had
raised purported claim based on 1972 schedule of rates by letter dated
24th May, 1974 (marked exhibit 5 in the reference), could not have
been favoured with award on basis thereof.
3.
He relies on order dated 1st December, 2021 of the Supreme
Court in Civil Appeal no.7738 of 2011 (Pranab Jyoti Das vs. The
General Manager and others), wherefrom paragraphs 4 and 5 are
extracted and reproduced below.
“4. The arguments of the appellant is that Ex.P-12,
schedule of items of work and quantities were revised as
450% above North Signature Not Verified Frontier
Schedule of rates on 5th June, 1992. Digitally signed by
DEEPAK SINGH Therefore, the appellant Date:
2021.12.04 13:00:16 IST Reason:is entitled to 450%
increase as on 5th June, 1992 above the schedule
of rates, over and above the rate quoted by the
appellant.
5. We do not find any merit in the argument raised.
// 3 //
Page 3 of 7
Ex.P-12 is an internal calculation sheet of the
department which was never circulated or became part
of the schedule of rates. Any noting in the file is not an
order on the basis of which the appellant could lay a
claim for higher rates. The High Court has declined the
claim of the higher rates on good and sufficient
grounds.”
He relies on another judgment of the Supreme Court in South East
Asia Marine Engineering and Constructions Limited vs. Oil India
Limited, reported in (2020) 5 SCC 164, paragraph 30, reproduced
below.
“30. From the aforesaid discussion, it can be said that
the contract was based on a fixed rate. The party, before
entering the tender process, entered the contract after
mitigating the risk of such an increase. If the purpose of
the tender was to limit the risks of price variations, then
the interpretation placed by the Arbitral Tribunal cannot
be said to be possible one, as it would completely defeat
the explicit wordings and purpose of the contract. There
is no gainsaying that there will be price fluctuations
which a prudent contractor would have taken into
margin, while bidding in the tender. Such price
fluctuations cannot be brought under Clause 23 unless
specific language points to the inclusion.”
He submits, said award be set aside in appeal.
4.
Mr. Mishra, learned senior advocate appears on behalf of
respondent contractor. He submits, aggregate sum awarded was
// 4 //
Page 4 of 7
Rs.4,18,566/- on rejecting most of the claims. Of this, claim, on
account of escalation by reliance on 1972 s