ORISSA HIGH COURT
B.R.SARANGI, S.K.PANIGRAHI, JJ
MALAYA K.MUND – Appellant
Versus
STATE and ORS. – Respondent
WP(C)/1907/2013
Finding of the Court:
The court found that the relief claimed by the petitioner is disputed one, and therefore, the court is not inclined to entertain this writ petition.
Final Decision: The writ petition is disposed of with liberty to the petitioner to pursue his remedy before the appropriate forum, if so advised.
Page 1 of 4
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.1907 of 2013
Malaya Kumar Mund
….
Petitioner
Mr. D.K. Rath, Advocate
-versus-
State of Odisha and others
….
Opposite Parties
Mr. A.K. Mishra, AGA
CORAM:
DR. JUSTICE B.R. SARANGI
MR. JUSTICE S.K. PANIGRAHI
Order No.
ORDER
04.01.2022
4.
1. This matter is taken up through hybrid mode.
2. Mr. D.K. Rath, learned counsel appearing for the petitioner
contended that the brief has been transferred from his office, for
which he has no instructions.
3. Mr. A.K. Mishra, learned Addl. Government Advocate
contended that the relief sought in the writ petition cannot be
granted as it is purely money claim and the same is disputed one.
To substantiate his contention, he has relied upon paragraph-5 of
the counter affidavit, which reads as follows:-
“5. That in reply to the averments made in
paragraph-2 of the writ petition, it is respectfully
submitted that the work “Slop protection/lining
work at vulnerable reaches of R.M.C. including
construction of service road on left bank of RMC
from RD-00 to 11 Km. (Reach-1) RD-00 to 6 Km.
// 2 //
Page 2 of 4
entrusted to the petitioner vide Divisional
Agreement No.8 F2 of 1995-96. The said work
was completed by 31.3.2000. After completion of
the work, the SDO, Right Canal Sub-Division
No.I, Mukhiguda who was in-charge of the work,
recorded the final measurement, prepared the final
bill observing all formalities in presence of the
petitioner and submitted before the Opp.party
No.4 on dtd.27.03.2001. Soon after the final
measurement was recorded the petitioner was
required to accept the final measurement with
settlement of all his claims as required under the
rules but the final bill with connected documents
were received in the office of the Opp.party No.4
without acceptance of final measurement by the
petitioner. Unless the final measurement was
accepted, it was not possible to initiate all
required steps to get the final deviation approved
for release of payment. Since 27.3.2001, the
petitioner remained silent without any valid
reason and actually accepted the measurement on
19.10.2009 i.e. after lapse of eight years and six
months, though it was the primary duty of the
petitioner to do so during the preparation of final
bill. The xerox copy of the page- 34 and 35 of MB
No.697/RCD-I witnessing the acceptance of
measurement by the petitioner is annexed
herewith vide Annexure-A/4
Due to the above inaction and non-co-
operation on the part of the petitioner, the
Opp.party No.4 could not forward the final
deviation statement of the work to his higher
authorities which is essentially required to be
approved before release of final payment as per
the condition of contract. After acceptance of final
measurement by the petitioner i.e. on 19.10.2009
the final deviation statement of the work has been
sent to the Opp.party No.3 and the matter is now
// 3 //
Page 3 of 4
under active consideration for approval by
competent authority observing all codal rules.
Similarly, regarding payment of price
escalation, it is to submit that during process of
the work, the price of materials incorporated in
the work increases or decreases, as a result of
increase or decrease in the average wholesale
price index (all commodities) and the petitioner
thereupon necessarily and properly pays in respect
of that material, such increased and decreased
price, then he shall be entitled to reimbursement
or liable to refund quarterly as per clause 32 of F2
contract. Therefore, the petitioner is required to
submit
his
reimbursement
claim
of
price
escalation quarterly during progress of work. In
the instant case, the petitioner remained silent for
a long period without any valid reason and
submitted his reimbursement claim towards price-
escalation on dtd.14.7.2009 i.e. after a lap
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.