HIGH COURT OF ORISSA
NANDA INFRA CONSTRUCTION PVT.LTD – Appellant
Versus
CHAIRMAN-CUM-MD,ORISSA INDUSTRIAL INFRASTRUCTURE DEVELOPMENT CORPORATION – Respondent
WP(C) 14022/2018
['M/S KAMAL BEHARI PANDA', '', 'S MISHRA', 'M/S DURGA PRASAD NANDA SR ADV', 'R K KANUNGO', 'B P PANDA', 'S MOHARANA', 'GOURANGA BEHARI JENA', 'M/S D N MOHAPATRA', 'J MOHANTY', 'J K NAYAK', 'P MOHANTY', 'S N DASH', '', 'P K PASAYAT', 'M/S BIBHU PRASAD DAS G MOHANTY A MOHANTY P A DASH']
1
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.14022 of 2018
Nanda Infra Construction Pvt.
Ltd., Angul
&..
Petitioner
Mr. Kamal Behari Panda, Advocate
Vs.
Chairman-cum-Managing,
Director, Orissa Industrial
Infrastructure Development
Corporation, Bhubaneswar
and Others
&..
Opposite Parties
Mr. P. K. Mohanty, Senior Advocate,
appearing along with P. Mohanty,
Advocate
(O.P. No. 1 to 3)
Mr. P. A. Dash, Advocate
(O.P. No. 4)
Mr. P.P. Mohanty, AGA
(O.P. No. 5)
CORAM:
DR. JUSTICE B.R. SARANGI
Mr. JUSTICE S. K. MISHRA
ORDER
28.07.2022
Order No.
9
This matter is taken up through hybrid mode.
2.
Heard Mr. K. B. Panda, learned Counsel for the
Petitioner; Mr. P. K. Mohanty, learned Senior Counsel
appearing along with Mr. P. Mohanty, learned Counsel for
Opposite Parties No. 1 to 3; Mr. P.A. Dash, learned Counsel
for Opposite Party No. 4 and Mr. P. P. Mohanty, learned
Additional Government Advocate for Opposite Party No. 5.
3.
Though Notice was issued to Opposite Party No. 6,
none appeared on his behalf.
4.
The Petitioner, being a Super-Class Contractor, has
filed this Writ Petition seeking to quash the Order dated
12.07.2018 under Annexure-18 issued by the Divisional
Head, Angul Division, rescinding Agreement No. 01-F2/16-
2
17, dated 07.06.2016 as per clause No. III(e) of the
conditions of contract.
5.
Mr. K. B. Panda, learned Counsel appearing for the
Petitioner vehemently contended that the impugned Order
dated 12.07.2018 has been passed by the Divisional Head,
Angul Division, without assigning any reason, which is
contrary to the Principles of Natural Justice. More so, it is
contended that as per Clause-III(e) of the conditions of
contract, to rescind the contract of which recession notice in
writing to the Contractor under the hand of the Divisional
Head/Executive Engineer shall be conclusive evidence and
the same has to be signed by such person and as such, though
such rescission of contract order was signed by the
Divisional Head, Angul Division, but the notice of the
rescission of contract has been given by Opposite Party No.
4, who is none else less but a Consultancy Authority vide
Annexure-5 Series dated 15.05.2018. Thereby, incompetent
person has issued notice against the Petitioner to rescind the
contract, which cannot be sustained in the eye of law. To
substantiate the case of the Petitioner, he has relied upon the
judgment of this Court in (M/s.) East Coast Constructions
Industries Ltd., Odisha v. State of Odisha and others, 2016
(II) CLR-359.
6.
Mr. P. K. Mohanty, learned Senior Counsel appearing
for Opposite Parties No. 1 to 3 contended that since the
Petitioner has not completed the work within the time
stipulated in the agreement itself, the Authority has taken
steps for rescinding the contract. It is further contended that
by virtue of interim Order, the Bank Guarantee has been
extended from time to time, but after 01.04.2021, it has not
3
been renewed. Therefore, it is contended that direction may
be given to the Petitioner to renew the Bang Guarantee so
that the Opposite Parties can take necessary steps in
accordance with law.
7.
Mr. P. A. Dash, learned Counsel appearing for
Opposite Party No. 4 contended that Opposite Party No.4
was engaged as Consultant to look after the work undertaken
by the Petitioner and, as such, except the consultant work, it
has not done anything, which will cause prejudice to the
Petitioner.
8.
Having heard learned Counsel for the parties and after
going through the records, it appears that the Opposite Party
No.1 invited bids from the Contractors vide Bid
Identification No.PC-EST-74/2015-16 dated 28.01.2016 for a
sum of Rs. 4873.19 lakh approximately. The work was to be
completed within a period of 12 calender months. In
response to Invitations for Bids, the Petitioner participated
and as such, he was selected to underta