2023 Supreme(Online)(P&H) 8213
HIGH COURT OF PUNJAB AND HARYANA
SANJAY KILOI DOPANA COOP SOCIETY LTD ETC – Appellant
Versus
FINANCIAL COMMISSIONER & PRINCIPAL SECRETRY IRRIGATION DEPT HRY AND ORS – Respondent
RSA 6568 2016
RSA-6568-2016 (O&M)
2023:PHHC:061036
Sr. No.218
IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH
RSA-6568-2016 (O&M)
Date of decision: 28.04.2023
Sanjay Kiloi – Dopana Co-operative Labour and Construction Society Ltd.
...Appellant
Vs.
The Financial Commissioner and Principal Secretary Irrigation Department,
Haryana and others
…Respondents
CORAM:
HON’BLE MR. JUSTICE ARUN MONGA
Present:
Mr. Ravinder Malik, Advocate
for the appellant.
Mr. S.S. Mann, Addl. A.G., Haryana.
****
ARUN MONGA, J. (ORAL)
For convenience, parties herein are addressed as per the recitals
before learned trial Court.
2.
Having suffered concurrent adverse findings by the two Courts
below, plaintiff is in second appeal before this Court assailing Ld. Trial
Court judgment and decree dated 17.12.2014, as upheld by Ld. First
Appellate Court vide its judgment and decree dated 16.05.2016, dismissing
its suit for recovery of Rs.7,07,200/- along with interest.
3.
Briefly stated, facts as noticed by Ld. Courts below, are that
plaintiff society authorized Ramphal Singh, Special Power of Attorney of
Sanjay, President of Society to file the present suit.
Page 1 of 8
ASHISH
2023.05.22 18:14
I attest to the accuracy and
integrity of this judgment/order
RSA-6568-2016 (O&M)
2023:PHHC:061036
3.1.
Plaintiff was awarded a contract to lay down pipe line to drain
out the flood water from RD-0 to RD-2650. The said task was named
“Constructing Baland Pipe Line Link Drain with RD-0 to RD-2650 out
falling into JLN Feeder at RD 185160-R. The total work assigned to
plaintiff was awarded at the cost of Rs.31,97,760/-. Thereafter, defendants
reduced the distance from RD-2650 to RD-2250 vide order dated
11.01.2010. Vide letter dated 20.05.2010, defendants again increased the
length from RD-2250 to RD-2650. Plaintiff completed the assigned work up
to RD-0 to RD-2250 on 29.06.2010. For the remaining work, a sump well
was to be constructed only after de-watering the vicinity. Plaintiff requested
permission for de-watering to construct the sump well on RD-185610-R JLN
feeder, but the defendants did not grant any permission. The material placed
on the site by plaintiff in expectation of permission was taken away by the
villagers stealthily as the same continued to be lying there for quite long
time. Thus, the plaintiff suffered monitory loss of Rs.99,272/- due to
negligence of defendants.
3.2.
Defendants prepared total bill of Rs.25,54,989/- for work done
by plaintiff. But only payment of Rs.19,45,041/- was cleared and balance
payment of Rs.6,09,948/- remained outstanding. An amount of Rs.97,252/-
deducted as security was also outstanding against defendants. Earnest
money of Rs.35,000/- was also not returned by defendants. Thus, total
amount of Rs.8,06,472/- was outstanding against defendants. Plaintiff time
and again raised demand from defendants for recovery of above said
Page 2 of 8
ASHISH
2023.05.22 18:14
I attest to the accuracy and
integrity of this judgment/order
RSA-6568-2016 (O&M)
2023:PHHC:061036
amount. Beleaguered plaintiff-society, as it then was, also served a legal
notice upon defendants but to no effect, hence the suit for recovery.
4.
Upon notice, defendants filed joint written statement taking
preliminary objections inter alia regarding locus standi, causal connection,
maintainability, jurisdiction, concealment of material facts etc.
4.1.
On merits, the defense was that length of drain was proposed to
be reduced and slope of pipe line was provided as 0.25 per 1000 ft. instead
of 0.15 per 1000 ft. but later on the length was restored as per the agreement.
Revised L-section was approved vide S.E., YWS Circle, Rohtak letter dated
20.05.2010 in which some modifications in design were made as per
demand of the farmers and site requirement. Plaintiff society neither
completed the work in full length assigned to it nor executed the work
according to PWD specification and design, as p