HIGH COURT OF JUDICATURE FOR RAJASTHAN - PRINCIPAL SEAT AT JODHP
M/S A CUBE ASSOCIATES – Appellant
Versus
UNION OF INDIA and ORS – Respondent
ARBAP 1/2017
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Arbitration Application No. 1 / 2017
M/s A Cube Associates, 61, Nehru Park, Deepak Colony, Jodhpur
Through Its Partner Ajay Yaday S/o Shri R.P. Yadav, Aged About
46 Years.
----Petitioner
Versus
1. Union of India Through the General Manager,, North Western
Railway, Jaipur.
2. The Chief Engineer,, North Western Railway, Jaipur.
3. The Additional Divisional Railway Manager,, North Western
Railway, Jaipur.
4. The Senior Divisional Railway Engineer (Central), North Western
Railway, Jodhpur.
----Respondents
_____________________________________________________
For Petitioner(s) : Mr.K.K.Shah
For Respondent(s) : Mr.Kamal Dave
_____________________________________________________
HON'BLE MR. JUSTICE SANGEET LODHA
Judgment
17
th May, 2017
1.
This arbitration application under Section 11 (6) of the
Arbitration and Conciliation Act, 1996 (for short “the Act”) has
been filed by the applicant for appointment of Arbitrator on
account of the respondent failing to appoint Arbitrator in terms of
the arbitration clause in the contract.
2.
The applicant was awarded a work of ‘Casual Renewal of
Sleeper, Casual Renewal of rail to replace worn out and wheel
burnt rails in SWF-JU-MJ Section, replacement of glued joints in
(2 of 8)
[ARBAP-1/2017]
SWF-JU-LN Section, through fitting renewal of 87.30 km. in MTD-
JU-LN Section (km. 569.21 to 656.51)UNDER ADEN/LINE/JU” for
Rs. 77,15,607 vide work order dated 11.11.13 issued by the
Senior Divisional Engineer, North Western Railway, Jodhpur. The
work was to be completed within a period of nine months. The
agreement was executed between the parties for execution of the
work on 16.12.13. The work could not be completed within the
stipulated period, however, the respondent extended the date of
completion as per requirement and the applicant completed the
work on 30.4.16. As per the condition of the contract, the final bill
was to be released within a period of 30 days from the date of
completion. The applicant applied for completion certificate but
the same was not issued and vide communication dated 3.6.16
issued by Senior Divisional Engineer, NW Railway, the applicant
was informed that a few of the works have not been completed
and accordingly, it was advised to got the completion period
extended and complete the work. The applicant made a request
for extension of time clarifying that though it is not bound to do
the work, the extension is applied for completion as proposed
taking into consideration the fact that its huge amount is at stake.
The non applicants extended the date of completion without
penalty vide letter dated 15.7.16. The dispute having arisen
regarding the payment of the final bill, the applicant made
representation dated 1.6.16 purportedly invoking clause 64 of
General Conditions of Contract (‘GCC’) to nominate an
independent and impartial Sole Arbitrator within 60 days for
resolving the dispute referred to therein. The request made as
(3 of 8)
[ARBAP-1/2017]
aforesaid was followed by yet another representation dated
24.11.16, made by the applicant invoking Clauses no. 63 & 64 of
the GCC for appointment of Arbitrator but to no avail. Hence, this
application.
3.
Learned counsel appearing for the non applicant contended
that Clause 63 of the GCC, in the first instance all disputes and
differences of any kind whatsoever arising out of or in connection
with the contract, whether during the progress of the work or after
its completion, whether before or after the determination of the
contract are required to be referred by the Contractor to the
General Manager, who in his turn is required to notify decision on
all matters referred to by the contractor in writing within a period
of 120 days except for the matters, which are specifically excluded
from the purview of the arbitration clause. Learned counsel
submit