HIGH COURT OF JUDICATURE FOR RAJASTHAN
ARUN BHANSALI
M/S KAMLA CONSTRUCTION COMPANY – Appellant
Versus
RAJASTHAN RAJYA – Respondent
ARBAP/21/2020
[2023/RJJD/004996]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Arbitration Application No. 21/2020
M/s Kamla Construction Company, Registered Partnership Firm
1-D-81, Jainarayan Vyas Colony, Tehsil And Dist. Bikaner.
----Petitioner
Versus
Rajasthan Rajya, District Collector, Bikaner.
----Respondent
For Petitioner(s)
:
Mr. Pradeep Choudhary.
For Respondent(s)
:
Mr. Saransh Vij for Mr. Sudhir Tak, AAG.
HON'BLE MR. JUSTICE ARUN BHANSALI
Order
10/02/2023
This application under Section 10 and 11 of the Arbitration
and Conciliation Act, 1996 (‘the Act’) has been filed by the
applicant seeking reference of dispute between the parties to
Arbitrator.
It is inter alia indicated that the applicant was issued a work
order dated 1.1.1996 for manufacture and supply of 20 lakh first
class bricks and an agreement No.7/1995-1996 was executed in
this regard. As per the order and contract, the work was to
commence from 16.1.1996 and was to be concluded in 12 months
i.e. by 15.1.1997.
It is claimed that the applicant earnestly commenced
implementation of the work order and supplied 20 lakh bricks by
31.10.1996, however, another order dated 31.10.1996 was issued
to the applicant for supply of additional 20 lakh bricks and based
[2023/RJJD/004996]
(2 of 6)
[ARBAP-21/2020]
on the said quantity, it was expected that the contract would be
extended till 15.1.1998.
It is then indicated in the application that for various reasons
on account of rains etc. instead of 40 lakh bricks, the applicant
was required to manufacture 45.50 lakh bricks, however, the
applicant was not made full and final payment by the respondents
in terms of Clause-10(a) of the agreement. It is claimed that on
account of delayed payment, the applicant is entitled for interest
on the outstanding payment.
It is then indicated that in terms of Clause-19 of the
agreement, any question, difference or objection in connection
with the agreement was to be referred to a sole arbitrator to be
appointed as per the procedure prescribed, based on which, the
applicant issued a notice dated 5.3.2020, however, as the
respondents have not followed the procedure prescribed under
Clause-19, they have lost the right to appoint arbitrator and,
therefore, a sole arbitrator be appointed.
A reply to the application has been filed by the respondents
inter alia with the submissions that the petitioner did not complete
the work in the stipulated time period i.e. 31.3.1997 and there
was a delay of more than a year in execution of the work order
and, therefore, the petitioner is not entitled to any relief.
Further submissions have been made that the applicant was
lying in the state of slumber as the dispute pertains to the year
1998 and the present application has been filed in 2020 after
issuing notice. The claim made is ex-facie barred by limitation
even as per Article 137 of the Limitation Act, 1963 and, therefore,
the application deserves dismissal.
[2023/RJJD/004996]
(3 of 6)
[ARBAP-21/2020]
No rejoinder to the reply has been filed.
Learned counsel for the applicant made submissions that the
claim made by the applicant is genuine, wherein, the respondents
have not made payment of huge outstanding amount to the
applicant and not only this, even the final bill has not been
prepared and, therefore, the plea raised pertaining to the claim
being barred by limitation has no substance. It was emphasized
that as the final bill has not been prepared so far, it cannot be said
that the claim is barred by limitation so as to seek dismissal.
Further submissions have been made that it is well settled
that the issue pertaining to the limitation has to be considered by
the arbitrator and this Court while examining the matter under
Section 11 of the Act, cannot determine the aspect of limitation.
Reference in this regard has been made to judgments in
Duro Felguera. S.A. v. Gangavaram Port Lim