Date of Order :
09.04.2014
HON'BLE MR. JUSTICE ALOK SHARMA
Mr. Mahendra Goyal, for the review petitioner-JDA.
Mr. S.M. Mehta, Sr. Advocate with
Mr. R.S Mehta, for the writ petitioner-Insurance Co.
BY THE COURT
This review petition has been filed by the JDA in
respect of the order dated 05.03.2012, passed by this Court.
Mr. Mahendra Goyal, appearing for the review
petitioner-JDA, which was earlier the non-petitioner in writ
petition, has submitted that the order dated 05.03.2012, passed
by this Court, is wrongly premised on a purported concession on
“instructions” by the counsel appearing in the writ petition for
the JDA. It has been submitted that no such “instructions” to the
counsel had been given based on which the order dated
05.03.2012 was passed. Counsel has drawn attention of this
Court to application No.14169 dated 29.03.2013 filed in this
review petition wherein it has been stated that after the receipt
of the certified copy of the judgment dated 05.03.2012, on
finding that the order has been passed on the “concession”
extended by the counsel representing the JDA, explanation of the
S.B. CIVIL REVIEW PETITION NO.301/2012
(2)
counsel was sought vide letter dated 13.04.2012. Therein it was
specifically stated that no instructions with regard to conceding
in the Court on the release of construction plans within three
weeks or otherwise had been given to the counsel. It was
submitted that in pursuance to the said letter dated 13.04.2012
by the JDA to its counsel, vide reply dated 17.04.2012, counsel
had merely circumvented the issue and instead stated that “the
best possible order in such circumstances was getting an order
which will continue till disposal of suit. Since the possession is
already with the petitioner, the order with regard to not
alienating the property has been passed by the Hon'ble court
due to great persuasion made by us. It is not understandable as
to what the petitioner will do with the property which is a
commercial plot without alienating the same, otherwise also this
order will last till disposal of suit and in other words the stay has
been granted by Hon'ble Court in the case where JDA has failed
to obtained any stay in the Trial Court. Despite of pendency of
suit and TI Application for such a long time. Even there is no
direction to approval of the plan and direction has been given to
consider and the release the plan in accordance with building
bylaws of 2010.” It was then submitted that the concession with
regard to the release of the building construction plans to the
petitioner-Company even while its title to the land in issue was in
dispute, was a concession on point of law in view of the fact that
as per the JDA Regulations, 1996 and thereafter amended
S.B. CIVIL REVIEW PETITION NO.301/2012
(3)
Regulations of 2000, on receipt of application for grant of
building permission, verification of the title of the owner of the
land is required. Counsel submitted that in these circumstances,
no concession for release of the building construction plans
while the title of the petitioner-Company thereto was in dispute
could have been given. Reliance has also been placed on Rule 6
(3) of the Rajasthan Urban Areas (Sub-Divisions Reconstitution
and Improvement of Plots) Rules, 1975 (hereinafter 'the Rules of
1975') stating that the said Rules are supplemental to the JDA
Building Bye-Laws of 1996-2000 and in terms thereof also an
application when received by the JDA either for sub-division,
reconstitution or improvement, proof of ownership of the land is
required to the requisite satisfaction o