SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Online)(HC) 2048

Shampa Sarkar, J
Mr. Birendra Bhagat – Appellant
Versus
Arch Infra Properties Private Limited – Respondent
CIVIL REVISIONAL APPLICATION CO 4354 of 2023



Advocates:
For the Appellants/Petitioners: Mr. Aniruddha Chatterjee, Mr. Aditya Kanodia, Mr. Rudrajit Sarkar
For the Respondents: Mr. Pronit Bag, Mr. Ashis Kr. Mukherjee, Mr. S. Prasad, Mr. Manmatha Mondal

An arbitration clause must clearly indicate the parties' intention to refer all disputes to an arbitrator; ambiguous clauses that limit scope to specific disputes do not constitute valid arbitration agreements.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 8 - Jurisdiction of courts to adjudicate on the existence of arbitration agreement - The court emphasized the necessity of a clear intention of parties to refer disputes to arbitration - Essential elements of a valid arbitration agreement were discussed, particularly the absence of clarity in arbitration clauses - Agreement with architect does not suffice as an arbitration clause for all disputes - The court ruled that the money claims under contract were outside the purview of the arbitration mechanism established. (Paras 2, 32, 53)

(B) Interpretation of arbitration clauses - A court must uphold commercial agreements in plain terms without invalidating clauses unnecessarily - Existing standard must be followed to determine intent of parties in arbitration agreement. (Paras 2, 54)

(C) Definitions of elements constituting valid arbitration agreement were reiterated from the precedent cases and statutory provisions, emphasizing the need for express and implied agreement between the parties for resolution of disputes. (Paras 43, 52)

Table of Content
1. order related to arbitration agreement. (Para 1 , 2)
2. details of the contractual obligations. (Para 3 , 4 , 5 , 6 , 10 , 11)
3. construction of dispute resolution clauses. (Para 13 , 14 , 15 , 16)
4. contention that clauses are not true arbitration agreements. (Para 18 , 19 , 22 , 28)
5. conclusion on lack of arbitration intention. (Para 39 , 44 , 53)
6. finding based on irrelevant facts. (Para 54)

1. The revisional application arises out of an order dated October 18, 2023, passed by the learned Judge, Commercial Court at Rajarhat in Money Suit No.38 of 2022. The learned court allowed an application dated December 16, 2022, filed by the opposite party under Section 8 of the Arbitration and Conciliation Act, 1996 , (hereinafter referred to as said Act of 1996).

2. The learned court observed as follows:-

    a) A commercial agreement between the parties had to be construed in a way that the terms used were understood in its plain, ordinary and popular sense.
    b) The immediate intention of the parties should be gathered from the plain reading of the terms of the agreement.
    c) The clause should be interpreted in such a manner, so as to give effect to the same, rather than invalidate the same.
    d) While construing an arbitration clause, a court must adopt a pragmatic and not a technical approach. Section 7 of the said Act, 1996, did not provide any particular form of the agreement. It would not be appropriate for the court to desist from upholding the validity of an arbitration agreement.
    e) The essential elements of an arbitration agreement had been fulfilled in the instant case, namely, existence of a dispute between the parties and intention of the parties to settle such dispute by a private tribunal.
    f) The agreement was in writing, and the parties were ad idem.
    g) Thus, the clause dealing with settlement of dispute by a skilled person, namely, the architect, was an arbitration clause. Although, the same may not have been happily drafted.

3. Mr.

Aniruddha Chatterjee, learned Advocate for the plaintiff/petitioner/contractor, drew the attention of this Court to the plaint case. The case of the plaintiff is discussed hereunder.

4. The suit was filed for recovery of money valued at Rs.6,68,24,995/-. The plaintiff as the proprietor of Bharat Construction (contractor) and the defendant had entered into a development agreement for construction of a residential housing complex, namely, ‘Starwood’. The proposed project comprised of seven buildings. The location of the same was Chinar Park, Rajarhat. Total number of eight (08) towers were to be constructed in the said complex.

5. The contractor started work on the basis of a letter of acceptance issued by the defendant on December 18, 2015. The possession was handed over to the contractor. On March 20, 2016, additional miscellaneous piling work was further awarded, which resulted in enhancing the scope of the original contract. Along with the contract, the defendant also made over a copy of the bill of quantity and/or schedule of items as also the work order.

The bill of quantity and schedule of items were later modified to some extent. The work granted by the defendant to the plaintiff was such that time was the essence and the entire project was agreed to be completed with 20 months from December 18, 2015. As time was the essence of the contract, obligations were cast on both sides. The obligations, as entailed in the agreement, could be summed up as follows :-

    a. The defendant would ensure a hindrance-free worksite immediately upon issuance of the letter of acceptance.
    b. The defendant as the contractor would ensure smooth access to the worksite for the plaintiff to commence and carry on the project within the stipulated time.
    c. The defendant would take all necessary steps to ensure that earth excavated at the construction site was shifted and disposed of at a suitable place.
    d. The defendant would ensure reasonable land space for labour hutments at the project site.
    e. The defendant would

                                                                          Click Here to Read the rest of this document
                                                                          1
                                                                          2
                                                                          3
                                                                          4
                                                                          5
                                                                          6
                                                                          7
                                                                          8
                                                                          9
                                                                          10
                                                                          11
                                                                          SupremeToday Portrait Ad
                                                                          supreme today icon
                                                                          logo-black

                                                                          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                                                                          Please visit our Training & Support
                                                                          Center or Contact Us for assistance

                                                                          qr

                                                                          Scan Me!

                                                                          India’s Legal research and Law Firm App, Download now!

                                                                          For Daily Legal Updates, Join us on :

                                                                          whatsapp-icon telegram-icon
                                                                          whatsapp-icon Back to top