1 (A/02/885)
STATE CONSUMER DISPUTES REDRESSAL COMMISSION
MAHARASHTRA, MUMBAI
FIRST APPEAL NO.A/02/885
1. The Brihanmumbai Electrict Supply &
Transport Undertaking
BEST Bhavan, BEST Marg,
Post Box No.192,
Mumbai 400 001.
2. Mr.R.P.Patel
Dy. General Manager (Supply)
The Brihanmumbai Electrict Supply &
Transport Undertaking
BEST Bhavan, BEST Marg,
Post Box No.192,
Mumbai 400 001.
3. Mr.Chandramohan
Chief Engineer (South)
The Brihanmumbai Electrict Supply &
Transport Undertaking
BEST Bhavan, BEST Marg,
Post Box No.192,
Mumbai 400 001.
4. Mr.M.Z.M.A. Sayed
Divisional Engineer
The Brihanmumbai Electrict Supply &
Transport Undertaking
BEST Bhavan, BEST Marg,
Post Box No.192,
Mumbai 400 001.
Appellant(s)
Versus
Mr.Harish Arjan Thakkar
Chotani Building
52/A, Proctor Road,
Mumbai 400 007.
Respondent(s)
BEFORE :
Mr.Justice S.P.Tavade, Hon’ble President
Smt.S.T.Barne, Hon’ble Judicial Member
2 (A/02/885)
ORDER
(Dated: 29th September, 2022)
Per : Smt.S.T.Barne, Hon’ble Judicial Member
1] The appellant Brihanmumbai Electric Supply & Transport Undertaking
and others have preferred this appeal against the Judgment and Order dated
30/04/2002 passed by the District Consumer Disputes Redressal Commission,
South Mumbai District.
2] The appellants are the original opponents and the respondent is the
complainant in the original complaint before the District Commission. They are
hereinafter referred as per their status in the consumer complaint. It reveals
from the record made available in appeal alongwith appeal memo that the
complainant is carrying business and opponents are engaged in supply of
electricity. The complainant was holding electricity meter Nos.0648047 and
0295900 in respect of electricity provided to his business premises. His average
consumption was between Rs.6000/- to Rs.7000/- per month. However, since
the month of January 1998, the meters started showing fluctuations in the
consumption of electricity. Hence, it was informed to the opponent vide letter
dated 21/08/1998 that he received inflated bill of Rs.17,331.95 in the month of
June 1998. Though the complainant followed this matter for about six months
the opponent No.1 did not take any corrective measure. On 19/02/1999 the
opponent No.1 informed the complainant that there was no reason to doubt the
accuracy. On 08/03/1999, the complainant again informed the opponent that
the meters were not functioning properly and they should replace the same. The
complainant disputed the bills under protest. As he was getting excess bills he
has removed two air conditioners, so that consumption will be reduced.
However, on 06/07/1999 the opponent No.5 informed him that the consumption
of his electricity was uniformed and there was no reason to doubt accuracy. It
was further informed to the complainant that on 22/06/1999 the meter was
3 (A/02/885)
inspected in fact no meter was inspected in his presence. The opponent No.1 on
23/06/1999 informed the complainant that during investigation they found
meter No.648047 faulty and they replaced the same on 23/06/1999. The
complainant was requested to pay excess charges for about 10 months towards
the said meter. Thereafter, also problem was not resolved. There were only 6
tube-lights and one fan in use. The complainant by letter dated 21/03/2000
informed the opponent that there was inordinate delay in redressing the
grievances and there was no justification for demand of excess bills and d