CONSUMER CASE NO. 1119 OF 2018
 
1. APOORV BANSAL
R/o A-54, East of Kailash
New Delhi - 110065
...........Complainant(s)
Versus 
1. M/S. VATIKA LTD.
Vatika Group 7th Floor, Sushant Lok-I, Block-A, Mehrauli-Gurgaon Road,
Gurgaon - 122002
Haryana
...........Opp.Party(s)

BEFORE: 
 HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT
 HON'BLE DR. S.M. KANTIKAR,MEMBER

For the Complainant :
For the Complainant : Ms. Himani Aggarwal, Advocate
For the Opp.Party :
For the Opposite Party : Mr. Ayshwarya Chander, Advocate

Dated : 28 Jan 2022
ORDER
1. The present amended Consumer Complaint has been filed under Section 21 of the Consumer Protection Act, 1986 (for short “the Act”)by the Complainant, Shri  Apoorv Bansal against Opposite Party Builder, M/s. Vatika Ltd. (hereinafter referred to as ‘the Builder’) seeking refund of the amount paid by him to the Builders towards purchase of the Residential Unit alongwith interest and compensation.  
2. The facts as narrated in the Complaint are that the Complainant had booked a Residential Apartment in the Project, namely “Tranquil Heights – Vatika India Next”, Sector 82A, Gurgaon to be developed by the Opposite Party Builder,by paying a booking amount of ₹8 lakh on 2.11.2013. The total Sale Consideration of the Apartment was ₹1,36,25,625/- (Rupees One Crore Thirty Six Lakh Twenty Five Thousand Six Hundred and Twenty Five only) which was to be paid in terms of Construction Linked Plan. Vide Allotment Letter, dated 29.09.2014,the Complainant was allotted Unit No. E-703 located on7th Floor in Tower No. E having Super Area of 2290 sq. ft. It is alleged by the Complainant that the terms of the allotment were simply dictated to him and he had no option except to sign the Allotment letter under duress. Further, in the Allotment Letter, no date for handing over the possession of the allotted Unit was mentioned and it was orally affirmed by the Builder that the possession of the subject Apartment would be handed over within three years from the date of booking i.e., by November, 2016. 
The Complainant made all the payments from time to time as demanded by the Opposite Party Builder. It is averred that after a long communication,  the Opposite Party Builder finally sent the Builder Buyer Agreement to the Complainant for execution Vide Letter dated 23.06.2015, whereby the total sale consideration of the allotted Unit was stated to be ₹1,65,73,875/- (Rupees One Crore Sixty Five Lacs Seventy Three Thousand Eight Hundred and Seventy Five Only). As per Clause 13 of the Agreement, the construction of the Building/Apartment was to be completed by the Builder within 48 months from the date of execution of the Builder Buyer Agreement, meaning thereby that the possession should have been handed over to the Complainant on or before 22.05.2019. Since, some of the terms and conditions of the Builder Buyer Agreements were one sided and totally in favour of the Opposite Party Builder, the Complainant refused to sign the same and requested the Builder either to change the disputed terms and conditions of the Builder Buyer Agreement or refund the amount deposited by him. However, no Builder Buyer Agreement was executed between the Complainant and the Opposite Party Builder. While the Complainant was awaiting the amended/fresh Builder Buyer Agreement, he came to know that the Tower E where he was allotted the Residential Unit, was not approved by the Competent Authorities and only Towers A and B were approved that too in October 2015. However, the Opposite Party Builder started raising demands from November 2013. Vide e-mail dated 09.11.2015, the Complainant requested the Opposite Party Builder to refund the deposited amount with interest @ 18% p.a. In response, vide email dated 10.11.2015, the Opposite Party Builder informed the Complainant that his request for cancellation of the booking could not be acceded to. Again, vide email dated 11.03.2017, the Complainant pointing out