(Delivered on 07/01/2021)
PER SHRI A. Z. KHWAJA, HON’BLE PRESIDING MEMBER.
1. Complainant – Mr. Mahesh M. Mulchandani resident of Dhantoli, Nagpur has moved the present Consumer Complaint under Section 17 of the Consumer Protection Act, 1986.
2. Short facts leading to the present complaint may be narrated as under:-
Complainant Mr. Mahesh M. Mulchandani claims to be resident at Dhantoli, Nagpur and was doing the business of running a Daily Needs Shop at Dhantoli. The No. 2- Sahara Prime City Limited claims to be reputed builders who were providing residential flats along with all possible amenities. The O.P. namely Sahara Prime City Limited had also given advertisement showing various amenities and comforts provided in the flat to be constructed by them and so the complainant was attracted by lucrative offers made by the O.P. Complainant- Mr. Mahesh Mulchandani therefore, entered into an agreement with the O.P. for purchase of one residential unit No. B6/406, Block No. B6 on fourth floor admeasuring 88.73 Sq. Mtrs. In the residential scheme being constructed at Mouza Gavasi (Manapur). Agreed cost of the residential unit was Rs. 22,20,000/- and same was payable in 38 monthly installments as stipulated in the agreement. The complainant has alleged that he has invested his hard earned money in purchasing proposed residential flat construct by the O.P. but despite the payments made by the complainant, the O.P. failed to perform their part of contract and did not complete the construction work of the building and also did not hand over the possession to the complainant despite sending letters to them. The complainant has already paid an amount of Rs. 22,48,566/- . The complainant has come to the conclusion that by not performing the part of contract and also not constructing the building as well as not hand over the possession of the promise unit, the O.P. Nos. 1 to 3 have indulged in deficiency in service and same amounted to unfair trade practice. Complainant- Mahesh Mulchandani was therefore left with no other option but to file present Complaint under section 17 of the Consumer Protection Act, 1986.
3. The O.Ps. have appeared and resisted the complaint by filing written version. The O.Ps. have also filed their written notes of argument on record. At the outset the O.Ps. have taken a plea that the complainant had booked the present unit with the sole intention to earn profit and so they do not fall within purview of definition of the ‘Consumer’ under the Consumer Protection Act, 1986. The O.Ps. have also taken a specific plea that their contract is also governed by Term No. 16 regarding Force Majure which implies the delay due to circumstances beyond the control of the company. The O.Ps. have taken a plea that the delay if any had taken place due to on going litigations between O.Ps. and SEBI before the Hon’ble Supreme Court and so the completion of all the projects had come to stand still.