NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
 
CONSUMER CASE NO. 170 OF 2008
 
1. SOCITY OF CATALYSTS
N-130B, Panchshila Park
New Delhi - 110 017
Delhi
...........Complainant(s)
Versus 
1. RAJ TRUST, R & M TRUST & ORS.
13th Floor, Raheja Towers, 26-27, M.G. Road, Through its Administrator Mr. Justice (retd) R.G. Vaidyanatha
Bangalore - 560 001
Karnataka
2. R & M TRUST
Through Mr.Chatru Menda, The Millenia, Nos 1 &2, Murphy Road,
Bangalore - 560 008
Karnataka
3. CHANDRU L. RAHEJA
Construction House A, 24th Road, Khar (West)
Mumbai - 400 052
Maharashtra
4. ARJUN M. MENDA
RMZ Corporation The Millennia, Tower B, Level 12-14, 1/2, Murphy Road, Ulsoor
Bangalore - 560 008
Karnataka
5. GOPAL L. RAHEJA
Construction House B, 2nd Floor, 623, Linking Road, Khar (West)
Mumbai - 400 052
Maharashtra
6. SANDEEP G. RAHEJA
House - B, 2nd Floor, 623, Linking Road, Khar (West)
Mumbai - 400 052
Maharashtra
7. RAJ A. MENDA
45/1, Fairfield Layout, Race Course Road
Bangalore - 560 001
Maharashtra
8. MANOJ A. MENDA
45/1, Fairfield Layout, Race Course Road
Bangalore - 560 001
Karnataka
9. NEEL C. RAHEJA
House - B, 2nd Floor, 623, Linking Road, Khar (West)
Mumbai - 400 052
Maharashtra
...........Opp.Party(s)

BEFORE: 
 HON'BLE MR. JUSTICE V.K. JAIN, PRESIDING MEMBER
 HON'BLE DR. B.C. GUPTA, MEMBER

For the Complainant :
Mr. Omesh Saigal, Advocate
Mr. Yatindra N. Vidyarthi, Advocate
For the Opp.Party :
For the Opposite Party No.2: Ex-parte
For the Opposite Party No.
3&9 : Mr. Kunal Vajani, Advocate
Mr. Pranaya Goyal Advocate
Mr. Shubham Kulshreshtha, Advocate
For the Opposite Party No.5: Deleted
For the Opposite Party No.6: Mr. Farrukh Rasheed, Advocate
For the Opposite Party No.
4, 7 & 8 : Mr. R. David, Advocate
Ms. Febin M. Varghese, Advocate

Dated : 19 Apr 2016
ORDER

JUSTICE V.K. JAIN, PRESIDING MEMBER

          The complainant claims to be a Voluntary Consumer Association and is registered under the Societies Registration Act and taking up the cases of consumers in various Forums, including Consumer Courts.  One Mrs. Janaki, owner of the certain land in village Sadahalli, Taluk Devnanhalli, District  Bangalore North, obtained sanction for converting  the said land from the agricultural to non-agricultural / residential purposes and then entered into an agreement dated 20.08.1990, followed by supplementary agreement dated 05.11.1990 and subsequent agreements dated 17.11.1990 and 13.07.1992 with opposite party No.1 Raj Trust.  Opposite Party No.1 prepared a scheme to develop the aforesaid land into a residential colony, and entered into a development agreement dated 23.09.1991 followed by supplementary agreement dated 01.09.1992 with opposite party No. 2 R & M Trust.  Residential sites in the aforesaid project were then sold by opposite party No. 1 Raj Trust to several buyers, for consideration and individual sale deeds in their favour were executed jointly by opposite party No.1 and Mrs. Janki.  Separate agreements were executed between plot buyers and opposite party No.2 R&M Trust for development of the plots sold to them by opposite party No.1, on payment of the agreed development charges.  It is alleged in the complaint that opposite party No.2 completed the development work in phase-I of the aforesaid project namely Jade Garden including construction of club house for recreation facilities, constructing roads etc. and generally carried out its obligation in respect of the said phase-I.  It is further alleged that after regular maintenance of phase-I, including its upkeep, security and management of the club house, Phase-I was handed over to the association of plot buyers.  It is further alleged that after completing or during the completion of phase I, opposite party took up the work of phase II and III of the said project and entrusted the development work for the said phases also to opposite party No.2.  According to the complainant, since phase-II to IV were not complete in all respects,  opposite party No.1