Per Shri S.R. Khanzode, Hon’ble Presiding Judicial Member
Heard Appellant-Mr.Ganesh Y. Aware in person at length on the point of admission.
2. Appellant takes an exception to an order dated 17/07/2013 passed in consumer complaint No.252/2011 (Shri Ganesh Yashwant Aware V/s. Executive Engineer, Maharashtra State Electricity Distribution Co. Ltd., Rajgurunagar, Pune) by Addl. District Forum, Pune.
3. The grievance of the appellant was that he resides at Alandi Devachi, Tal. Haveli, Dist. Pune and for that purpose has taken energy supply from Maharashtra State Electricity Distribution Co. Ltd. (hereinafter referred to as ‘Electric Company’) and his consumer no. is 1760113388964. He had taken said energy supply on 12/12/2000. However, he started actually residing in the premises from 04/04/2003. On 15/05/2003 his energy meter was replaced as defective and new electronic meter was installed. According to the appellant till 15/05/2003 he was entitled only to pay meter rent. Thereafter, appellant could not pay the energy consumption bills due to his illness. In the month of December 2005 appellant has received a bill for `24,000/-. On 04/12/2005 appellant represented to the Electric Company to reduce the amount of bill and also tried to point out to the Electric Company as to how the bill for consumption of 4883 units for period of 19 months was calculated wrongly. However, he was asked to pay the arrears in five installments and accepted `5,000/- towards arrears. On 31/03/2005 Electric Company had floated a scheme to rebate 100% interest for late payment, but said facility and benefit was not given to the appellant. In the meantime, on 12/12/2006 Electric Company had accepted `1,600/- from the appellant towards part payment of arrears and promised him to redress his grievance. On 07/02/2007 meter of the appellant was taken for inspection and it was found ‘O.K.’ and as per current bill `2,600/- were accepted from the appellant. Appellant asked for a report of installation of energy meter in the year 2003 but it was not given. Till 07/10/2009, Electric Company had received `15,600/- from the appellant. It is the grievance of the appellant that due to wrong reading and defective meter he was required to pay interest on arrears and accordingly he made a grievance in writing on 17/10/2010 but in vain. In the meantime, he had taken the matter to the Consumer Disputes Redressal Forum established by the Electric Company under the Indian Electricity Act, 2003. However, his grievance was not redressed there. It is further submitted on behalf of the appellant that during 02/01/2005 till end of 2006 his energy consumption was minimum and though his energy consumption was increased during the period 2008 to 2010, to pay energy consumption charges for `27,340/- was not proper. According to him he is not liable to pay `27,340/- towards energy consumption charges. However, Electric Company had received `34,955/- from him. According to him `2,053/- was at his credit as per his calculation. Bill dated 29/10/2011 showing arrears of `48,430/- was wrong and his energy supply was thereafter discontinued on 03/10/2011 without giving pre-intimation or notice and therefore, consumer complaint was filed with a relief that bill for `48,430/-, supra, should be corrected and E