STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Mr. Sudeep Singh Sabharwal, s/o Late Sh. D.S. Sabharwal, 100, Lakhi Nagar, Club Road, Jorhat, Assam 785001
……Appellant/Judgment Debtor/Opposite Party
V e r s u s
Smt.Baljit Kaur w/o S.Sachinpreet Singh Ketth, R/o H.No.1101, Phase-X, SAS Nagar, Mohali, Punjab.
....Respondent/Decree Holder/complainant
Appeal under Section 27-A of the Consumer Protection Act, 1986.
BEFORE: JUSTICE SHAM SUNDER (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
Argued by: Sh. Rohit Sapra, Advocate for the appellant.
PER JUSTICE SHAM SUNDER (RETD.), PRESIDENT
This appeal is directed against the order dated 13.02.2013, rendered by the District Consumer Disputes Redressal Forum-I, UT, Chandigarh (hereinafter to be called as the District Forum only), in Criminal Petition No.106 of 2012, titled as Smt.Baljit Kaur Vs. M/s J.S. Dwellers Pvt. Limited, vide which, Mr. Sudeep Singh Sabharwal, Managing Director/Director of the Opposite Party, was convicted and sentenced to undergo simple imprisonment, for a period of one year, and to pay a fine of Rs.10,000/-, in default of payment whereof, to undergo further imprisonment for a period of 6 months.
2. The facts, in brief, are that the Consumer Complaint bearing No.293 of 2011, was filed by Smt.Baljit Kaur, Decree Holder/complainant, on the allegations that the Judgment Debtor/Opposite Party, floated a scheme, under the name and style “Cresent Apartments” at Baddi(HP), with a proposal to develop apartments, on the total land, comprising Khasra No.652/475, Khewat/Khatouni No.61/70, situated in Village Saner, Hadbast No.161, P.O. Manpura, Prg. Tehsil Nalagarh, District Solan. Attracted by the advertisements, in leading newspapers, giving rosy pictures, that the project had been duly approved by the Himachal Pradesh Govt., the complainant, alongwith her family, visited the site, and deposited a sum of Rs.25,000/-, with the Opposite Party, vide cheque dated 24.12.2005. Another amount of Rs.1 lac, as part price of the said apartment, was paid by the complainant, on 10.05.2006. In all, an amount of Rs.1.25 lacs, was paid by the complainant, towards the part price of said apartment. The total price of the apartment, booked by the complainant, consisting of three bedrooms drawing/dining, kitchen and toilets, ground floor, was fixed at Rs.14.05 lacs, which included wood work, sanitary, electrical fittings etc. Apartment Buyer`s Agreement dated 27.05.2006 (Annexure C-4), was executed between the parties, at Chandigarh. According to Clause No.14 of the said Agreement, the builder was to complete the project, within 2 years, from the start of construction. Even after the lapse of two years, the time stipulated, in the said Agreement, no progress was made to complete the construction of apartment, despite the fact that the complainant was ready and willing to perform her part of the contract.
3. In the middle of June, 2009, the complainant visited the site, and found the office of the Opposite Party locked. It came to the knowledge of the complainant that Mr.Sudeep Singh Sabharwal, Managing Director/Director of M/s J.S. Dwellers Pvt. Limited, Judgment Debtor/Opposite Party, had been arrested by the Chandigarh Police, in a cheating case. It was stated that neither the construction of apartment, was completed by the Opposite Party, nor the question of delivery of possession thereof could arise, nor the refund of amount deposited by the complainant was made to her, despite various requests.