NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

 

CONSUMER CASE NO. 1512 OF 2017

1. ANIL RAWAT & ANR.

S/o Sh. Manohar Singh Rawat, R/o C6-501, The Legend, Sector-57

Gurgaon

Haryana-122002

2. MADHU RAWAT

W/o Sh Anil Rawat, R/o C6-501, The Legend, Sector-57

...........Complainant(s)

Versus

1. CLARION PROPERTIES LIMITED & 2 ORS.

Through its Directors,
Regd. Office at:
34, Babar Lane, Bengali Market,

New Delhi-110001

2. AJANTA BUILDERS PVT. LTD.

Through its Directors,
Regd. Office at:
20, Ansari Road, Daryaganj,

New delhi-110006

3. AEZ INFRATECH PRIVATE LIMITED

Through its Directors,
having its office at: 707, 7th Floor,
Chiranjiv Tower, 43, Nehru Place

New Delhi

...........Opp.Party(s)

CONSUMER CASE NO. 1513 OF 2017

1. GOPAL GUPTA & ANR.

S/o L.M. Gupta, aged about 46 years, R/o C2-302, The Legend, Sector 57

2. LLA GUPTA

W/o Gopal Gupta, aged about 43 years, R/o C3-303, The Legend, Sector 57,

Through its Directors, Regd. Office at:
34, Babar Lane, Bengali Market,

Through its Directors,
Regd. Office at:
20, Ansari Road, Daryaganj

New Delhi-110006

Through its Directors, having its office at:
707, 7th Floor, Chiranjiv Tower, 43, Nehru Place

CONSUMER CASE NO. 1539 OF 2017

1. MAHESH KUMAR SHARMA & ANR.

S/O MALIRAM SHAMA, R/O C6-103, THE LEGEND SECTOR 57,

GURGAON - 122002

2. RUCHI SHARMA,

W/O MAHESH KUMAR SHARMA, R/O C6-103, THE LEGED SECTOR 57,

1. CLARION PROPERTIES LTD. & 2 ORS.

THROUGH ITS DIRECTORS. REGD. OFFICE AT 34, BABAR LANE, BENGALI MARKET

NEW DELHI - 110001

2. AJANTA BUILDERS PVT. LTD,

THOUTGH ITS DIRECTOR REGD. OFFICE AT 20, ANSARI ROAD, DARYAGANJ,

NEW DELHI - 110006

3. AEZ Infratech Private Limited.,

707, 7th Floor, Chiranjiv Tower, 43, Nehru Place,

New Delhi

CONSUMER CASE NO. 1540 OF 2017

1. MINI WAHI

W/o. Lt. Col. YK Wahi (Retd), R/o. C6-201, The Legend, Sector - 57

Haryana

2. -

-

3. -

Through Its Directions, Office at: 34, Babar Lane, Bengali Market,

New Delhi - 110001

2. Ajanta Builders Pvt. Ltd.

Through its Directors, Regd. Office at: 20, Ansari Road, Daryaganj,

New Delhi - 110006

3. AEZ Infratech Private Limited

Through its Directors, Having its Office at: 707, 7th Floor, Chiranjiv Tower, 43, Nehru Place,

CONSUMER CASE NO. 1541 OF 2017

1. RITI KALRA

D/o. Dalbir Singh Bhatia, R/o. C3-303, The Legend, Sector - 57,

Gurgaon - 122002

Regd. office at 34, Babar Lane, Bengali Market,

2. Ajanta Builders Pvt. Ltd.

Through its Director,
Regd. office at 20, Ansari Road, Daryaganj,

New DElhi - 110001

Through Its Director, Having Its Office at 707, 7th Floor, Chiranjiv Tower 43, Nehru Place,

CONSUMER CASE NO. 1706 OF 2017

1. PROMIL SACHDEV & ANR.

W/o Wg. Commander Yogesh Sachdev(Retd.),
R/o C1-301, The Legend, Sector 57,

Gurgaon-122002

2. WG. COMMANDER YOGESH SACHDEV(RETD)

Through their AR, Sh. Aman Aditya Sachdev,
R/o H. No. 346, DDA, Hauz Khas,

New Delhi-110016

Through its Directors,
Regd. Office At:
34, Babar Lane, Bengali Market,

2. AJANTA BUILDERS PVT. LTD,

Through its Directors,
Having its office at:
707, 7th Floor, Chiranjiv Tower, 43, Nehru Place,

BEFORE:

&nbsp

HON'BLE MR. JUSTICE RAM SURAT RAM MAURYA,PRESIDING MEMBER

HON'BLE DR. INDER JIT SINGH,MEMBER

For the Complainant :

Mr. Bhupender Pratap Singh, Advocate


with Ms. Ranjita Pal, Advocate

For the Opp.Party :

Ms. Kaadambari, Advocate with

Ms. Ayushi and Mr. Sahil, Advocates

Advocates:
For the Petitioner: MR. BHUPENDER PRATAP SINGH
For the Respondent:

ORDER

DR.INDER JIT SINGH, MEMBER

1.   The present batch of Consumer Complaints (CCs) have been filed by the Complainant(s) against Opposite Parties as detailed above, inter alia praying for directions to the OP(s) for:-

(vi)    Refund of Administration Charges.

(vii)   Refund of illegally charged amount on account of excessive area

Charges.

(viii)  Refund of illegally charged amount on account of BOCW Welfare

Cess.

(ix)    Refund of illegally charged amount on account of failure to provide Italian marble floors in drawing and dinning room promised in the agreement/brochure and shown in the sample flat.

(x)     Refund of illegally charged amount on account of failure to provide hardwood doors promised in the agreement/brochure and shown in the sample flat.

 

(xi)    Refund of illegally charged amount on account of failure to provide Kohler fittings in the bathrooms as promised in the agreement/brochure and shown in the sample flat.

(xii)   Compensation for delay in providing basement parking.

(xiii)  Compensation for non -existent and deficient 

          common area facilities.

xiv)   Compensation for exposing complainants to extreme risk and hazard

on account of poor mechanical, electrical and plumbing work.

(xv)   Compensation for physical and mental harassment/agony.

(xvi)   Pay cost of litigation.

(xvii)  Grant pendent lite and future interest @18% p.a. on the prayed

amounts under different heads stated above.

(xviii) Return the satisfaction note, no objection note, handing over/ taking

over note and other blank papers which were forcibly got signed by it from the complainants before the registration of the apartments.

2.       Since the facts and question of law involved and the reliefs prayed for in these complaints are similar/identical and against the same Opposite Parties except for minor variations in the dates, events and flat numbers etc., which are summarized in the Table at Annexure –A, these complaints are being disposed off by this common order. However, for the sake of convenience, Consumer Complaint (CC) No. 1512 of 2017 is treated as the lead case and facts enumerated herein under are taken from CC 1512/2017.

3.   Notice was issued to the OP(s).  Parties filed Written Statement/Reply, Rejoinder, Evidence by way of an Affidavit and Written Arguments/Synopsis etc. as per details given in the Table at Annexure-A.  The details of the flats allotted to the Complainant (s)/other relevant details, based on pleadings of the parties and other records of the case are also given in the Table at Annexure-A.

4.  Brief facts of the case, as emerged from the pleadings of the parties and other case records are that:-

i)    A flat No. C6-501 in the project of OP-1, ‘The Legend’, in Sector 57, Gurgaon was originally allotted to one Mr. Q.R. Gupta (HUF) on 18.11.2006 and subsequently a Buyer’s Agreement was executed between Q.R. Gupta HUF and OP-1 on 18.11.2006.  Thereafter, the Complainants purchased the said unit from the original allottee and stepped into the shoes of original allottee by means of an endorsement by OP-1 on the said Buyer’s Agreement dated 18.11.2006. Vide letter dated 11.09.2008, OP-1 transferred all rights, direct or indirect, pertaining to the said flat, in the name of complainants, alongwith complete deposited amount of Rs.48,04,344/- against the said flat.

 

ii)      As per said Agreement dated 18.11.2006, the committed date of completion of the said unit is 36 months from the date of start of construction of the tower in which the said unit is located or from the execution of the agreement, whichever is later, subject to force majeure circumstances and on receipt of all payments punctually as per agreed terms.

iii)     The construction of the tower where the said flat was located was completed on 14.10.2009 and OP-1 applied for Occupation Certificate (OC) on 14.10.2009.  OP-1 obtained OC on 12.10.2010 and thereafter issued final call letters dated 23.10.2010 to complainants asking them to take over the possession of the unit.   A

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top