NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
V.K. JAIN, J
CAPITAL GREENS FLAT BUYER ASSOCIATEION – Appellant
Versus
DLF UNIVERSAL LIMITED – Respondent
| Table of Content |
|---|
| 1. overview of consumer complaints and defendants. (Para 1 , 2 , 3 , 4) |
| 2. nature of complaints and the society's registration. (Para 5 , 6 , 7 , 8 , 9) |
| 3. understanding of the 'super area' in the agreements. (Para 12 , 13 , 14 , 15) |
| 4. definitions and implications of club and parking charges. (Para 16 , 17 , 18 , 19 , 20) |
| 5. examination of force majeure claims and delays. (Para 21 , 22 , 23) |
| 6. developer's liability regarding possession delays. (Para 24 , 25 , 26 , 27 , 28) |
| 7. determining compensation for delayed possession. (Para 31 , 32 , 33 , 34) |
| 8. final orders for compensation and liabilities. (Para 35 , 36 , 37) |
ORDER
JUSTICE V.K. JAIN, PRESIDING MEMBER
The opposite party namely DLF Universal Limited (hereinafter referred to as “Developer”) is the developer of the large residential project namely “DLF Capital Greens” developed on the land situated at Shivaji Marg, Moti Nagar, New Delhi. 2870 residential apartments in 23 residential towers have been constructed by the developer in three phases, the first and second phase comprising of 10 towers each and the third phase comprising of three towers. Laresen & Toubro was appointed as the Principal Contractor for constructin
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.