SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Online)(NCDRC) 532

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
JUSTICE DEEPA SHARMA, PM
REENA KAPUR & ANR. – Appellant
Versus
M/S. EMAAR MGF LAND LIMITED – Respondent
CONSUMER CASE NO. 2696 OF 2017



Advocates:
For the Appellants/Petitioners: Mr. Abhishek Singh
For the Respondents: Mr. Rabin Majumder

The court established that failure to deliver possession as per contract terms entitles consumers to full refund and interest, reaffirming consumer rights under the Act.

Headnote:(A) Consumer Protection Act, 1986 - Section 2(1)(d) - Delay in possession - Complainants booked units in a residential project with commitments of timely delivery; however, the opposite party failed to hand over possession as stipulated. The court found the opposite party responsible for the delay and ordered a complete refund of ₹2,00,46,068/- with interest. (Paras 1-7)

(B) Jurisdiction - The opposite party’s claim that complainants are not consumers was dismissed for lack of evidence showing the intention of investment. The complainants are indeed consumers under the Act. (Paras 5-6)

(C) Legal Principle - The court reiterates that the consumer cannot be made to wait indefinitely for possession and is entitled to seek a refund with compensation. (Para 5)

Facts of the case:
Complainants made multiple payments for two units in a project, facing delays beyond the agreed period. They sought refunds and compensation for mental anguish.

Findings of Court:
The opposite party failed to deliver possession timely and lacks evidence to disprove consumer status. Refund and interest are warranted.

Issues: The primary issues were the delivery timelines, consumer status, and the implications of the Builder Buyer Agreement.

Ratio Decidendi: Timely possession is a contractual obligation; failure to deliver entitles the consumer to compensation. The opposite party's claims lacked substantiation.

Result: Complaint allowed, refund ordered.

Table of Content
1. complainants booked units under contract for residential property. (Para 1)
2. opposite party's denial of consumer status lacked evidence. (Para 2 , 6)
3. consumer is entitled to timely possession; opposite party failed to meet obligations. (Para 3 , 4)
4. failure to deliver possession leads to entitlement for refund. (Para 5)
5. court's order for refund and compensation. (Para 7)
ORDER

JUSTICE DEEPA SHARMA, PRESIDING MEMBER

1. The present complaint has been filed with the contention that complainants are joint allottees of two units in the project of the opposite party called ‘Gurgaon Greens’ located at Sector-102, Gurgaon, Haryana. The opposite party had represented that they were in the process of constructing luxury apartments residential society and had also represented that they had secured all necessary layout / development plans/licenses etc. from the competent authorities. They also represent that on payment of Rs.7,50,000/-, they shall issue an allotment letter and within 90 days execute Builder Buyer Agreement. This representation was made in the month of August / September 2012 and on 17.10.2012 the complainants made initial payment of Rs. 7,50,000/- respectively against each of the two units towards booking amount, for which no receipt was issued on the said date. A Provisional Allotment Letter for the units GGN220601 and GGN220602 were issued on 27.01.2013 and demand of Rs.7,22,010.60/- and Rs.7,40,550/- were also raised against the two units which included 50% of EDC and 50% of IDC which was payable latest by 21.02.2013. The complainants made payment of said sum on 22.02.2013. Since there was delay of one day, the complainants were made to pay penalty of 24% interest for such delay. A demand was also raised vide letter dated 01.03.2013 for Rs.8,78,730/- and Rs.8,88,000/- respectively for the two units and the payments had been made by the complainants within time. It was only on 04.04.2013 that the opposite party asked the complainants to execute two Builder Buyer Agreement which had been provided by them. The total consideration price of the unit GGN220601 was Rs.1,28,84,456.02/- and for other unit GGN220602, the consideration price was Rs.1,30,69,850.02/- excluding parking and some other charges. They were made to sign the Builder Buyer Agreement as refusal would have resulted in forfeiture of the amount which they had already paid. They, therefore, signed the Builder Buyer Agreement as they did not have any other option. The complainants had opted for the Construction Linked Payment Plan. The delivery time of the two units was 36 months. The complainants also took loan from HDFC Bank. Two separate loans were taken for two units. A Tripartite Agreement dated 04.04.2013 was entered into between the complainants, opposite party and the bank and, thereafter, the loan was disbursed. The loan was given on an interest of 10.40% per annum on a variable rate linked plan. The rate of interest increased to 10.75% in 2013 and currently it is 9.45%. Between the period April 2013 to June 2017, the complainants continued to make the payment as per demands. Till 26.07.2017, the complainants disbursed all instalments sent by the opposite party and they had paid Rs.99,52,654/- against unit no.GGN220601 and sum of Rs.1,00,93,414/- against unit no.GGN220602. The project as per the representation of the opposite party was to be completed within 36 months from the date of first payment i.e. by October, 2015 and the units were to be handed over along with all amenities. Even if, period of 36 months were to commence from the date of signing of the Builder Buyer Agreement, the units were to be delivered by April 2016. It was alleged that when the units were not handed over within the stipulated period, they sent several emails to the opposite party and the opposite party kept changing the delivery dates and all the time gave them new delivery date. It is submitted that vide email dated 18.01.2017, the opposite party had u









Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top