2022 Supreme(Online)(NCDRC) 91
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
CONSUMER CASE NO. 664 OF 2020
1. MOHAMMAD FAIZAN IQBAL
S/o. Mohammad Idris,
R/o. 608, Style Building,
Mankhool, Dubai,
UAE
...........Complainant(s)
Versus
1. EMAAR MGF LAND LIMITED
Through its Directors,
at 306-308,
Square One, C-2,
District Centre,
Saket, South Delhi,
New Delhi - 110 017
...........Opp.Party(s)
BEFORE:
 
HON'BLE MR. JUSTICE R.K. AGRAWAL,PRESIDENT
HON'BLE DR. S.M. KANTIKAR,MEMBER
HON'BLE MR. BINOY KUMAR,MEMBER
For the Complainant :
For the Complainant : Mr. Aditya Parolia, Advocate
Ms. Sumbul Ismail, Advocate
For the Opp.Party :
For the Opposite Party : Mr. Rajeev Agarwal, Advocate
For the Petitioner: M/S. PSP LEGAL
For the Respondent:
ORDER
“It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession.By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016.This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement.A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC.There was in any event a prayer for refund.”
6.1. In the present case, admittedly the Appellant – Builder obtained the Occupancy Certificate almost 2 years after the date stipulated in the Apartment Buyer’s Agreement. As a consequence, there was a failure to hand over possession of the flat to the Respondent – Flat Purchaser within a reasonable period. The Occupancy Certificate was obtained after a delay of more than 2 years on 28.08.2018 during the pendency of the proceedings before the National Commission.
In Lucknow Development Authority v. M.K. Gupta, [(1994) 1 SCC 243] this Court held that when a person hires the services of a builder, or a contractor, for the construction of a house or a flat, and the same is for a consideration, it is a “service” as defined by Section 2 (o) of the Consumer Protection Act, 1986. The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service.
In Fortune Infrastructure &Anr. v. Trevor D’Lima& Ors., [(2018) 5 SCC 442] this Court held that a person cannot be made to wait indefinitely for possession of the flat allotted to him, and is entitled to seek refund of the amount paid by him, along with compensation.
6.2. The Respondent – Flat Purchaser has made out a clear case of deficiency of service on the part of the Appellant – Builder. The Respondent – Flat Purchaser was justified in terminating the Apartment Buyer’s Agreement by filing the Consumer Complaint, and cannot be compelled to accept the possession whenever it is offered by the Builder. The Respondent – Purchaser was legally entitled to seek refund of the money deposited by him along with appropriate compensation.
6.3. The National Commission in the Impugned Order dated 23.10.2018 held that the Clauses relied upon by the Builder were wholly one-sided, unfair and unreasonable, and could not be relied upon.
The Law Commission of India in its 199th Report, addressed the issue of ‘Unfair (Procedural & Substantive) Terms in Contract’. The Law Commission inter-alia recommended that a legislation be enacted to counter such unfair terms in contracts. In the draft legislation provided in the Report, it was stated that :
“A contract or a term thereof is substantively unfair if such contract or the term thereof is in itself harsh, oppressive or unconscionable to one of the parties.”
6.6. Section 2 (r) of the Consumer Protection Act, 1986 defines ‘unfair trade practices’ in the following words :
“‘unfair trade practice’ means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice …”, and includes any of the practices enumerated therein. The provision is illustrative, and not exhaustive.
6.7. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder.
The contractual terms of the Agreement dated 08.05.2012 are ex-facie one-sided, unfair, and unreasonable. The incorporation of such one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by