SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION

NEW DELHI

 

REVISION PETITION NO. 1914 OF 2023

(Against the Order dated 18/05/2023 in Appeal No. A/79/2023 of the State Commission Delhi)

1. M/S TDI INFRASTRUCTURE LTD.

D-92, GROUND FLOOR, LAJPAT NAGAR 1

SOUTH

DELHI

...........Petitioner(s)

Versus

1. MR. CHAMAN LAL JINDAL & ANR.

C-31, NEHRU ENCLAVE, BEHIND JAIN HARDWARE, NARELA ROAD, ALIPUR

NORTH WEST

2. MRS. NEERJA JINDAL

C-31, NEHRU ENCLAVE, BEHIND JAIN HARDWARE, NARELA ROAD, ALIPIUR

...........Respondent(s)

BEFORE:

&nbsp

HON'BLE MR. JUSTICE KARUNA NAND BAJPAYEE,PRESIDING MEMBER

FOR THE PETITIONER :

MS. KANIKA AGNIHOTRI, ADVOCATE

Dated : 29 August 2023

Advocates:
For the Petitioner: M/S. SKV ASSOCIATES
For the Respondent:

ORDER

1.       This revision petition has been filed under Section 21 (b) of the Act 1986 in challenge to the Order dated 18.05.2023 in Appeal No. 79 of 2023 of the State Commission Delhi arising out of Order dated 22.12.2022 of the District Commission in Complaint no.151 of 2018.

2.       Briefly the chain of events which led to the filing of the present revision petition is thus:

          District Commission vide its Order dated 22.12.2022 allowed the complaint and directed the opposite party to refund the amount of Rs.11,35,400/- along with interest @ 12% p.a. from the date of deposit till realization within a period of 4 weeks from the date of receipt of order.  Rs. 1,00,000/- was awarded towards compensation for harassment and mental agony.  It was also ordered that in case of delay in the payment beyond 4 weeks the opposite party had to pay interest @ 18% p.a. for the delayed period. Apart from it a sum of Rs. 25,000/- was awarded towards costs.

3.       Aggrieved by the same the opposite party preferred an appeal before the State Commission but with a delay of 10 days.

4.       Vide its impugned Order dated 18.05.2023 State Commission refused to condone the aforesaid delay and dismissed the appeal preferred by the petitioner on  the point of limitation.

5.       Ordinarily, the Bench could have issued notice to the respondents and waited for them to appear.  But such a course would have inevitably delayed the process of adjudication for an indefinite period of time as in the wake of pendency of cases it is not very likely that the matter could be taken up at an early date. The Bench in that eventuality might also have to stay the operation of the order passed by fora below.  Adopting such a course could have possibly been potentially detrimental to the cause of consumer justice.  Hence, keeping in perspective the nature of the impugned Order and its narrow canvas which does not involve any complicated questions of law or fact, being a simple matter of dismissal on the ground of short delay in filing the appeal, the Bench deems it just and appropriate to decide the matter on the basis of the record and not to procrastinate it any further.

6.       Heard the learned counsel appearing for the petitioner and have perused the record including inter alia the Order dated 22.12.2022 of the District Commission, the impugned Order dated 18.05.2023 of the State Commission and the memo. of petition.

7.       Learned counsel for the petitioner during the course of her submissions, has reiterated the grounds taken in the delay condonation application. Contention is that the delay of 10 days in filing the appeal may not be termed as either inordinate or inexplicably drawn out.  Submission is that the certified copy of the Order dated 22.12.2022 was received by the petitioner from the District Commission only on 19.01.2023.  On 20.01.2023 the counsel for the petitioner was informed about the Order dated 22.12.2022 and he was instructed to prepare an appeal assailing the Order of the District Commission.  Submission is that since the project is situated in Haryana requisite time was spent in retrieving the documents from the site and only thereafter the appeal could be drafted and approved and thus a delay of 10 days occurred.  

8.       While dealing with the issue in question here regarding the limitation period, its breach and the availability or non-availability of sufficient cause to condone the delay where the appeal has been filed after the lapse of limitation period, the Bench deems it appropriate to first observe that the law on the point of limitation wherever it is provided has to be respected and complied with and in no case ought to be shelved with apathy or be blissfully ignored. Eventually, whether or not sufficient cause to condone delay is available or made out turns out to be a question of fact in each case and we have to see and keep in perspective the complete factual matrix and the syllogism of contextual circumstances und

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top