M.P.STATE CONSUMER DISPUTES REDRESSAL COMMISSION

PLOT NO. 76, ARERA HILLS, BHOPAL (M.P.)

Revision Petition No.37/2014

Atmaram Soni

… Petitioner

Vs.

Fullerton India Credit Co. Ltd.

… Respondents

BEFORE;

HON’BLE SHRI JUSTICE RAKESH SAKSENA, PRESIDENT

HON’BLE SMT. NEERJA SINGH, MEMBER

COUNSEL FOR THE PARTIES:

SHRI S.R. SONI, LEARNED COUNSEL FOR PETITIONEWR.

SHRI R.K. KAIMATHIYA, LEARNED COUNSEL FOR RESPONDENT.

O R D E R

( PASSED ON 13 .10.2015 )

The following order of the Bench was delivered by

Smt. Neerja Singh, Member.

This revision is by the complainant, aggrieved by

the order dated 11.3.14, passed by District Consumer

Disputes Redressal Forum, Bhopal, in Complaint Case No

392/12.

2.

The petitioner filed a complaint before the District

Forum, alleging deficiency in service on the part of the

opposite parties, Fullerton India Credit Company Ltd.

: 2 :

3.

During pendency of the complaint, on 27.9.13, he

filed an application requesting the Forum not to take the

reply of the opposite parties on record. He averred that

advocate, Shri Rajkumar, had appeared on behalf of the

opposite parties on 22.11.12, and had filed his Vakalatnama.

He should have filed the reply to the complaint within 30

days. The petitioner alleges that the reply which was filed

after a delay of 8 months, on 20.8.13, is a clear violation of

Section 13(1)(k) of the Consumer Protection Act, 1986. He

further submitted that the Shri Rajkumar’s Vakalatnama is

on behalf of opposite party No. 1, whereas the reply has

been filed on behalf of both the opposite parties.

4.

The District Forum dismissed the application on

the ground that the order sheet of 7.8.13 clearly mentions

the fact that instead of opposite party No. 2, opposite party

No. 1 was erroneously declared ex-parte. To rectify this

clerical error an application had been filed by the opposite

party No. 1, on 22.11.12. This error was then rectified vide

order dated 7.8.13. Hence the reply filed on 20.8.13 is within

the limitation period.

5.

Heard.

: 3 :

6.

A perusal of the record shows that the opposite

party No. 1 gave an application for setting aside the ex-parte

order on 22.11.12. The Forum, first dismissed the

application on 6.3.13, then allowed it on 7.8.13, holding the

ex-parte order to be a clerical mistake. The District Forum

undoubtedly erred in reviewing its own order. However, the

petitioner did not challenge this order which attained finality.

On the day the Forum set aside the ex-parte order, i.e.

7.8.13, the opposite party filed their reply and documents.

Hence, there was no delay on their part in filing the reply.

They could have filed the reply only after the ex-parte order

was set aside. Thus the application of the petitioner alleging

a delay of more than 8 months on the part of the opposite

parties in filing the reply was rightly dismissed by the District

Forum.

7.

In the result, we find no merit in this revision. It is

dismissed, but with no order as to costs.

(JUSTICE RAKESH SAKSENA) (SMT. NEERJA SINGH)

PRESIDENT MEMBER