O R D E R
( PASSED ON 13 .10.2015 )
The following order of the Bench was delivered by
Smt. Neerja Singh, Member.
This revision is by the complainant, aggrieved by
the order dated 11.3.14, passed by District Consumer
Disputes Redressal Forum, Bhopal, in Complaint Case No
392/12.
2.
The petitioner filed a complaint before the District
Forum, alleging deficiency in service on the part of the
opposite parties, Fullerton India Credit Company Ltd.
: 2 :
3.
During pendency of the complaint, on 27.9.13, he
filed an application requesting the Forum not to take the
reply of the opposite parties on record. He averred that
advocate, Shri Rajkumar, had appeared on behalf of the
opposite parties on 22.11.12, and had filed his Vakalatnama.
He should have filed the reply to the complaint within 30
days. The petitioner alleges that the reply which was filed
after a delay of 8 months, on 20.8.13, is a clear violation of
Section 13(1)(k) of the Consumer Protection Act, 1986. He
further submitted that the Shri Rajkumar’s Vakalatnama is
on behalf of opposite party No. 1, whereas the reply has
been filed on behalf of both the opposite parties.
4.
The District Forum dismissed the application on
the ground that the order sheet of 7.8.13 clearly mentions
the fact that instead of opposite party No. 2, opposite party
No. 1 was erroneously declared ex-parte. To rectify this
clerical error an application had been filed by the opposite
party No. 1, on 22.11.12. This error was then rectified vide
order dated 7.8.13. Hence the reply filed on 20.8.13 is within
the limitation period.
5.
Heard.
: 3 :
6.
A perusal of the record shows that the opposite
party No. 1 gave an application for setting aside the ex-parte
order on 22.11.12. The Forum, first dismissed the
application on 6.3.13, then allowed it on 7.8.13, holding the
ex-parte order to be a clerical mistake. The District Forum
undoubtedly erred in reviewing its own order. However, the
petitioner did not challenge this order which attained finality.
On the day the Forum set aside the ex-parte order, i.e.
7.8.13, the opposite party filed their reply and documents.
Hence, there was no delay on their part in filing the reply.
They could have filed the reply only after the ex-parte order
was set aside. Thus the application of the petitioner alleging
a delay of more than 8 months on the part of the opposite
parties in filing the reply was rightly dismissed by the District
Forum.
7.
In the result, we find no merit in this revision. It is
dismissed, but with no order as to costs.