SUPREME COURT OF INDIA
Justice S.J. Mukhopadhaya Chairperson, Justice A.I.S. Cheema Member (Judicial), Mr. Kanthi Narahari Member (Technical)
Navin Raheja. – Appellant
Versus
Shilpa Jain & Ors. – Respondent
Subject
Insolvency
NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI
Company Appeal (AT) (Insolvency) No. 864 of 2019
IN THE MATTER OF:
Navin Raheja
….Appellant
Vs.
Shilpa Jain and Others
….Respondents
Present:
For Appellant:
Mr. Salman Khurshid, Senior Advocate with
Mr. Abhijeet Sinha, Mr. Saurabh Kalia, Ms.
Amna Darakhshan, Ms. Saloni Purohit, Mr.
Saikat Sarkar, Mr. Kamesh Ved, Mr. Rohan
Mazumdar and Mr. Aditya Shukla, Advocates.
For Respondents: Mr. Arunav Patnaik, Ms. Mahima Sinha, Ms.
Shikha and Ms. Anandini Kumar, Advocates for
R1 & 2.
Mr. Neeraj Sharma, Advocate.
Mr. Arvind Nayar, Senior Advocate with Mr.
Samarjit, Mr. Rohan, Ms. Malika, Ms. Bomita
Singh and Ms. Aparjita, Advocates.
Mr. Piyush Singh and Mr. Aditya, Advocates in
I.A. No. 2724/2019.
Mr. Sanajeet Patnaik, Mr. Setyan Chaturvedi,
Mr. Vikas and Mr. Sumit Malhotra, Advocates
for I.A. No. 2746/2019.
Mr. Sukrit Kapoor, Advocate in I.A. No.
2869/2019.
2
Company Appeal (AT) (Insolvency) No. 864 of 2019
J U D G M E N T
SUDHANSU JYOTI MUKHOPADHAYA, J.
Pursuant to an application filed by Ms. Shilpa Jain and Mr.
Akash Jain (allottees) (1st and 2nd Respondents) under Section 7 of the
Insolvency and Bankruptcy Code, 2016 (“I&B Code” for short), the
Adjudicating Authority (National Company Law Tribunal), Special
Bench, New Delhi, by impugned order dated 20th August, 2019 initiated
‘Corporate Insolvency Resolution Process’ against ‘Raheja Developers
Ltd.’- (‘Corporate Debtor’).
2.
The Appellant, Shareholder/ Promoter has challenged the order
alleging fraudulent and malicious initiation of proceedings with an
intent for any purpose other than for the resolution of insolvency or
liquidation. It was also alleged that the application under Section 7 was
barred by limitation and was otherwise not maintainable on different
grounds.
Brief facts of the case:-
3.
The 1st and 2nd Respondents- allottees had booked an apartment
in the Residential Project- ‘Raheja’s Sampada’ being developed by the
‘Corporate Debtor’. In pursuance of the same, the ‘Corporate Debtor’
issued a joint allotment letter dated 3rd August, 2012 and executed a
Flat Buyer’s Agreement dated 3rd August, 2012. They disbursed total
3
Company Appeal (AT) (Insolvency) No. 864 of 2019
Rs.86,62,691/- to the ‘Corporate Debtor’ on different dates as
mentioned in Part-IV of Form-1 (application under Section 7). In
support of the claim, receipts issued by the ‘Corporate Debtor’ and
ledger account of the ‘Corporate Debtor’ were enclosed.
4.
It was alleged that as per Clause 4.2 of the Buyer’s Agreement,
possession of the Apartment was to be provided within 36 months
commencing from 3rd August, 2012 which came to an end on 3rd
August, 2015 but the construction was not completed.
5.
As per Clause 4.2, in case the construction is not complete within
time the ‘Corporate Debtor’ is under obligation to pay the allottee(s)
compensation @ Rs.7/- per sq. ft. of the super area per month for the
entire period of such delay. The said Clause 4.2 also postulates that the
aforesaid compensation @ Rs. 7/- per sq. ft. of the super area per
month for the entire period of such delay was to be adjusted at the time
of conveying the apartment and not earlier and it will be treated as
distinct charge.
6.
On filing of the application under Section 7, the ‘Corporate
Debtor’ took specific plea that the notice of possession was issued as
back as on 15th November, 2016 and in spite of repeated request to take
possession, the allottees have refused to take possession.
7.
It was also brought to the notice of the Adjudicating Authority
(National Company Law Tribunal) that the ‘Corporate Debtor’ had filed a
4
Company Appeal (AT) (Insolvency) No. 864 of 2019
Writ Petition before the Hon’ble Supreme Court of India challenging the
constitutional validity of explanation to Section 5(8)(f