2025 MarsdenLR 177
HIGH COURT MALAYA KUALA LUMPUR
QUANTUM HYRDROMECH SDN BHD – Appellant
Versus
NINE HUNDRED BUILDERS SDN BHD & ANOTHER CASE – Respondent
[Originating Summons No: WA-24C-25-02/2024 & WA-24C-29-03/2024 ]
Important Points
Subject
Construction Law - Adjudication
Act Referred
Headnote
(B) Natural Justice - Requirement for fair hearing and consideration of evidence - The court emphasized that dissatisfaction with the adjudicator's findings does not constitute a breach of natural justice. (Paras 20, 41, 44)
(C) Jurisdiction - Adjudicator's authority to decide on matters referred to adjudication - The adjudicator's decisions on variation claims and other issues were found to be within her jurisdiction as per the provisions of CIPAA. (Paras 24, 36)
Facts of the case:
The disputes arose from a construction contract where NHB claimed payments for work done, while Quantum sought to set aside the adjudication decision made in favor of NHB. The adjudicator awarded NHB sums for work completed, including additional variation claims and late payment interest. (Paras 6-17)
Findings of Court:
The court found that Quantum failed to establish grounds to set aside the adjudication decision, and NHB met the criteria for enforcement of the adjudicated amount. (Paras 46-49)
Issues: The main issues included whether the adjudicator acted beyond her jurisdiction and whether there was a denial of natural justice in the adjudication process. (Paras 19, 20)
Ratio Decidendi: The court held that the adjudicator's findings were within her jurisdiction and that Quantum's grievances related to factual determinations rather than procedural fairness. (Paras 44-46)
Result: The Setting Aside Application was dismissed, and the Enforcement Application was allowed.
JUDGMENT
Introduction
[1] These suits involve the application by:
(a) Quantum Hyrdromech Sdn Bhd ('Quantum') pursuant to ss 13, 15 and 16 of the Construction Industry Payment and Adjudication Act 2012 [Act 746] ('CIPAA') in Originating Summons No WA- 24C-25-02/2024 ('O.S. No 25') to set aside the Adjudication Decision dated 19 January 2024 ('AD') by the learned Adjudicator, Low Pei Voon ('Adjudicator') and to stay the AD pending the disposal of application to set aside the AD ('Setting Aside Application'); and
(b) Nine Hundred Builders Sdn Bhd ('NHB') pursuant to s 28 of the CIPAA in O.S. No. WA-24C-29-03/2024 ('O.S. No 29') to enforce the AD ('Enforcement Application').
[2] By consent of the parties, the prayer for a stay of the AD pending the disposal of the Setting Aside Application was allowed on the date of the hearing.
[3] After having considered the affidavit evidence and the submissions of the parties, the Court had, on 15 August 2024, I had dismissed the Setting Aside Application and allowed the Enforcement Application.
[4] The full grounds for the decision are set out in the succeeding part of this judgment.
The Cause Papers
[5] The cause papers for each application are as follows:
Setting Aside Application:
(a) Quantum's O.S. dated 26 February 2024 (encl 1);
(b) Quantum's Affidavit In Support ('AIS') affirmed by its Director, Chong Set Tat on 26 February 2024 (encl 2);
(c) NHB's Affidavit In Reply ('AIR') affirmed by its Director, Goo Kian Peng on 25 March 2024 (encl 4); and
(d) Quantum's AIR affirmed by the same deponent on 8 April 2024 (encl 5).
Enforcement Application:
(a) NHB's O.S. dated 4 March 2024 (encl 1);
(b) NHB's AIS affirmed by the same deponent on 4 March 2024 (encl 2);
(c) Quantum's AIR affirmed by the same deponent on 25 March 2024 (encl 3);
(d) Quantum's Notice of Intention to Use Affidavit in O.S. 25 (encl 2) dated 25 March 2024 (encl 4); and
(e) NHB's Notice of Intention to Use Affidavit in O.S. 25 (encl 4) dated 9 April 2024 (encl 5).
Background Facts
[6] Quantum is a private limited company incorporated in Malaysia with an address at C-8-5, Plaza Mont Kiara, No 2, Jalan Kiara, Mont Kiara, 50480 Kuala Lumpur.
[7] NHB is also a private limited company incorporated in Malaysia with an address at No 144, Jalan PUJ 3/8, Taman Puncak Jalil, Bandar Putra Permai, 43300 Seri Kembangan, Selangor.
[8] By the Letter of Award dated 6 March 2019 ('LOA'), Quantum appointed NHB as the sub-contractor for the project known as "Design, Submission, Obtaining Approval from Authorities and Subsequently Supply, Delivery, Installation, Construction, Testing and Commissioning, and Maintenance of Proposed Upgrading Existing Sewage Treatment Plant Module 2 (Phase A) to Cater for Additional 20,000 P.E for Cadangan Pembangunan Perumahan Dan Perniagaan Di Atas Lot 934, 982, 1246, 1286, 1851 Dan 3513, Mukim Rawang, Daerah Gombak, Selangor Darui Ehsan" for a contract sum of RM4,200,000.00 ('Project').
[9] On 28 July 2023, NHB issued the Payment Claim pursuant to s 5 CIPAA containing the following statements.
[10] NHB claimed that it has completed its scope of works for the Project on 16 December 2019 and all the rectification works within the Defects Liability Period ('DLP') of 12 months ie by 15 December 2020.
[11] On 26 March 2021, NHB submitted its Revised Final Claim for the value of permanent work done and materials on site, which included variation works, amounting to RM288,624.73.
[12] Subsequently, on 12 May 2021, NHB issued an invoice for the sum of RM393,624.73 consisting of the Final Claim and 2nd moiety of the retention sum (RM105,000.00).
[13] On 26 May 2023, Quantum issued the Sub-Contractor's Work Done Certificate No 12 (Final) ('PC No 12') amounting to a negative sum of RM72,405.60 upon release of the 2nd moiety of the retention sum.
[14] NHB contended that Quantum had under-valued and under-certified or wrongly certified NHB's value of work done in PC No 12. NHB claimed for the sum of RM393,624.73.
[15] Quantum did not