2025 MarsdenLR 392
HIGH COURT MALAYA SHAH ALAM
TRANSKON SDN BHD & ANOR – Appellant
Versus
GETO GLOBAL CONSTRUCTION TECH MALAYSIA SDN BHD – Respondent
[Civil Appeal No: BA-12BC-10-08/2024]
Important Points
Subject
Civil Law - Contract Law
Headnote
(B) Contractual Obligations - The court found that the supply contract was binding, and prior negotiations were nullified by the signed agreement. The defendants failed to establish non-compliance with the contract terms. (Paras 14, 18)
(C) Notice Requirement - The court ruled that a notice of demand is a prerequisite for claims against a guarantor, reversing the lower court's decision that no notice was required. (Paras 26, 36)
(D) Penal Notice - The court disallowed a penal notice in a purely monetary judgment, emphasizing that such enforcement should follow specific provisions. (Paras 34, 36)
Facts of the case:
The plaintiff claimed RM423,650.36 for supplied goods, which the defendants disputed on grounds of non-compliance and procedural errors in the original judgment. The 1st Defendant counterclaimed RM292,161.79 for damages. (Paras 3-5)
Findings of Court:
The appeal was partially allowed; the court confirmed the binding nature of the Sale Contract but overturned aspects related to notice requirements and interest rates. (Paras 36)
Issues: The main issues were whether the parties were bound by the Sale Contract, the requirement of notice to the guarantor, and the appropriateness of imposed interest rates. (Paras 11)
Ratio Decidendi: The court established that contractual obligations bind parties as per the signed agreement, that notice is necessary for guarantor claims, and that penal notices should not be included in monetary judgments. (Paras 26, 34)
Result: The appeal was allowed in part, with specific findings overturned. (Paras 36)
Introduction
[1] This is an appeal by the Appellants against the judgment delivered by the Learned Sessions Court Judge after full trial.
[2] The reference to the parties remain as per the original suit. The Appellants were the 1st and 2nd Defendants and the Respondent was the Plaintiff in the original suit at the Sessions Court.
B. Brief Background
[3] This case was filed by the Plaintiff claiming for the outstanding payment payable to it by the 1st Defendant and the 2nd Defendant as the guarantor to the 1st Defendant relating to the supply Self-Climbing Platform Framing Module ("SCP") by the Plaintiff to the 1st Defendant for the development project at Mesa Hill, Phase 4, Persiaran Ikmu BBN, Bandar Nilai Utama ("the Project").
[4] The Plaintiff had supplied the SCP based on the 1st Defendant's orders but the 1st Defendant had failed to pay the Plaintiff a sum of RM423,650.36 for the supply received by it.
[5] The 1st Defendant has objected to the Plaintiff's claims on the basis that the Plaintiff has failed to supply in accordance to the specification requested by it and due to the Plaintiff's failure to supply accordingly, the 1st Defendant filed a counterclaim of RM292,161.79 for the damages and losses suffered by it.
[6] The 2nd Defendant being the provider of a Personal Guarantee and Indemnity to the Plaintiff opposed the Plaintiff's claims against him on the basis that it was made pre-maturely as no notice of demand was made to him prior to making the claims
[7] In order to recover the unpaid sum, the Plaintiff filed a civil action at the Sessions Court via suit No BA-A52C-17-10/2022.
C. Sessions Court'S Decision After Full Trial
[8] This is the Defendants' appeal against the entire Judgment of the Learned Sessions Court Judge Puan Rafiqha Hanim Binti Mohd Rosli dated 14 August 2024 where she had allowed the Plaintiff's claim with costs of RM10,000.00 and dismissed the 1st Defendant's Counterclaim with costs of RM5,000.00 [see pgs 13-14 Part A Record of Appeal ("RA")].
[9] The Plaintiff's claims were allowed at the Sessions Court as follows:
a. Payment of the sum of RM423,650.36 as at 27 July 2022;
b. Interest at the rate of 1.5% per month on the outstanding sum calculated from the date of default until full settlement;
c. Interest at the rate of 5.0% per year on the outstanding sum calculated from the date of judgment until full settlement;
d. An Order for payment of total sum within 14 days from the date of judgment; and
e. A Penal Notice Pursuant To r 45 Of O 7 Of The Rules Of Court
D. Grounds Of Appeal By The Defendants
[10] That the Learned Sessions Court Judge had erred in facts and law on the following grounds:
i. That the Learned Sessions Court Judge had decided that all parties are bound to the Sale Contract dated 16 October 2020 and that "tiada sebarang ketidakpatuhan dalam Kontrak Jualan", although the Defendants had shown that the Self-Climbing Platform (SCP) supplied by the Plaintiff were for the length of only 217.617 meter and not in accordance to the perimeter of the building of 240.0 meter as stated in the Sale Contract dated 16 October 2020.
ii. That the Learned Sessions Court Judge had decided that "Defendan Pertama telah gagal membuktikan bahawa mereka telah mempertikaikan jumlah amaun yang dituntut" when at all material times, the Defendants had via letters dated 29 May 2021, 15 July 2021 and 8 July 2022 raised their complaints to the Plaintiff on the issue of non-compliance related to the building perimeter term for the SCP supplied by the Plaintiff.
iii. That the Learned Sessions Court Judge had decided that the Defendants did not consider the building perimeter when the Plaintiff supplied the SCP although evidenced that upon installing the SCP the building perimeter will be remeasured within 1-2 months after fixing the same.
iv. That the Learned Sessions Court Judge had decided that 'tiada sebarang tindakan daripada Plaintif yang menunjukkan terdapatnya suatu penerimaan ke atas Pesanan Beli