SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 2562

HIGH COURT MALAYA KUALA LUMPUR
BESJAYA MAJU SDN BHD – Appellant
Versus
HIM DEVELOPMENT SDN BHD & ORS – Respondent
[Civil Suit No: WA-22NCvC-324-06/2023]



Petitioner Advocates:Karen Isabel Wilfred ,Respondent Advocate: Ooi Tuan Leng,Tang Hui Jun,Chiam Jia Yann

The court ruled that failure to fulfill conditions precedent in a Joint Venture Agreement constitutes a breach, and COVID-19 disruptions do not excuse non-performance.

Headnote:(A) Joint Venture Agreement - Conditions Precedent - COVID-19 Act 2020 - The Plaintiff claimed damages for breach of contract under a Joint Venture Agreement dated 10 November 2014, asserting the First Defendant's failure to fulfill obligations. The court found that the First Defendant did not meet conditions precedent, and delays were not excused by the COVID-19 pandemic. (Paras 11, 12, 17, 20, 41)

(B) Breach of Contract - The court ruled that the First Defendant breached the Joint Venture Agreement by failing to complete the project within the stipulated timeline, despite implied consent to extensions not negating the obligation to perform. (Paras 18, 24)

(C) Liability of Guarantors - The Second Defendant and the estate of the Deceased were held jointly and severally liable under the Guarantee for the First Defendant's obligations, as the Joint Venture Agreement remained valid. (Paras 40, 42)

Facts of the case:
The Plaintiff entered into a Joint Venture Agreement with the First Defendant for land development, which included a deposit payment and obligations for obtaining necessary approvals. The First Defendant failed to complete the project within the agreed timeline, leading to the Plaintiff's claim for damages. (Paras 2, 3, 5)

Findings of Court:
The court found that the First Defendant breached the Joint Venture Agreement, and the Plaintiff was entitled to RM2,425,000.00 in damages, RM1,282,533.63 in interest, and RM120,000.00 in costs. (Paras 42)

Issues: The court addressed whether the conditions precedent were fulfilled, if the Defendants breached the agreement, and the applicability of the COVID-19 Act for relief. (Paras 11)

Ratio Decidendi: The court concluded that the First Defendant's failure to obtain all necessary approvals constituted a breach, and the COVID-19 pandemic did not excuse this failure. The implied consent to extensions did not negate the obligation to perform. (Paras 24, 30)

Result: The Defendants are to pay the Plaintiff RM2,425,000.00, RM1,282,533.63 in interest, and RM120,000.00 in costs.

JUDGMENT

Roz Mawar Rozain J:

[1] This case presents a classic intersection of contractual obligations, commercial reliance, and the consequences of non-performance in a high-stakes joint venture development. As emerged at trial, this dispute is not merely about delayed approvals and missed deadlines but about the expectations and responsibilities of parties engaged in a sophisticated land development agreement.

[2] The Plaintiff asserts its right to claim contractual entitlements under their Joint Venture Agreement for land development dated 10 November 2014 (JVA). The First Defendant and its guarantors (the Second Defendant and one Lai Hoong Sung (the Deceased) with now the Third and Fourth Defendants cited in this suit as they are the co-administrators of the Deceased's estate) argue that the contract should be deemed terminated due to unfulfilled conditions precedent, raising critical questions about waiver, extensions by conduct, and liability.

Agreed Facts

[3] The following facts were agreed upon by all the parties and remain undisputed:

(a) The JVA between the Plaintiff and the First Defendant that they had executed on 10 November 2014 is for a residential development project on land held by the Plaintiff under H.S.(M) 26010, Lot P.T. 40200 and H.S.(M) 26533, Lot P.T. 40593.

(b) The First Defendant had made a deposit payment of RM200,000.00 as per cl 3 of the JVA to the Plaintiff. The payment by the First Defendant was made in two tranches (RM30,000.00 and RM170,000.00).

(c) The First Defendant had successfully amalgamated the two pieces of land for development and subdivided the development land into 16 individual lots.

(d) The Second Defendant and the Deceased executed a Guarantee and Indemnity Agreement on the same date as the JVA - 10 November 2014 (the Guarantee) whereby they had jointly and severally undertook and guaranteed the First Defendant's obligations under the JVA including the payment of RM2,425,000.00 (the total after deducting the deposit payment of RM200,000.00) with interest at 8% per annum from the agreed completion date of 10 May 2018 until full settlement.

(e) The Second Defendant and the Deceased were directors of the First Defendant at the material time and through cl 2(f) of the Guarantee, it was agreed that their obligations will continue to exist until released through the implementation of the Guarantee, regardless of any resignation as director, unless the Plaintiff agrees in writing to substitute the director who resigned.

(f) The Plaintiff had not, at any time, given consent to replace any of the guarantors under the Guarantee.

(g) The Second Defendant and the Deceased agreed that their liability under the Guarantee shall not in any way be relieved, diminished or affected by death, their insanity or any incapacity (cl 2(1) of the Guarantee).

(h) The Plaintiff's cause of action under the Guarantee continues to exist against the estate of the Deceased based on the provisions of the Guarantee and in accordance with s 8(1) of the Civil Law Act 1956 .

(i) This action by the Plaintiff is commenced against the Third and Fourth Defendants as personal representatives for the estate of the Deceased according to O 15 r 6A of the Rules of 2012 (RoC).

Evidence Adduced At Trial

[4] At trial, the Plaintiff called upon its representative (PW1) who gave evidence on the Plaintiffs entitlement under the JVA and the First Defendant's failure to perform its contractual obligations. PW1 testified that the Plaintiff had contributed the lands for the joint venture project. In return, it was entitled to 3.5 units of double-storey linked houses or their monetary equivalent of RM2,625,000.00 as stipulated under the JVA.

[5] PW1 claimed that the joint venture project was delayed beyond the agreed 4 years (ending on 10 November 2018). Despite approvals such as the layout plan being secured on 18 July 2018, the First Defendant had failed to complete the joint venture project as agreed under the JVA. The Plaintiff's evidence highlighte


Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top