SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 1645

HIGH COURT MALAYA KUALA LUMPUR
PANTAI GREEN DEVELOPMENT SDN BHD – Appellant
Versus
ANCUBIC CAPITAL SDN BHD & ORS – Respondent
[Civil Suit No: WA-22NCvC-325-06/2022]



Petitioner Advocates:Yudistra Drama Dorai,William Ch'ng Wei Lim,Calise Lee Yen Hsien ,Respondent Advocate: Lee Kwee Lam

A plaintiff must possess legal capacity and valid authority to maintain a trespass claim, which was lacking due to an invalid Power of Attorney and absence of possession.

Headnote:(A) Powers of Attorney Act 1949 - Sections 6 and 7 - Action for trespass - Plaintiff alleged unlawful entry on land under a Joint Venture Agreement and Power of Attorney - Plaintiff lacked legal capacity to sue as it did not possess independent rights under the Power of Attorney - Court found the Power of Attorney invalid due to lack of consideration and fixed duration - No evidence of possession of the land by the plaintiff at the material time - Claims for damages and vicarious liability dismissed - Third-party proceedings rendered academic. (Paras 14, 20, 21, 29, 52, 53)

(B) Trespass - To establish a claim, plaintiff must prove possession and unlawful entry - Court reaffirmed that unauthorised entry constitutes trespass regardless of damage - No trespass found as D2 had consent to occupy land from D3, a registered proprietor. (Paras 29, 30, 34)

(C) Vicarious Liability - To impose liability, there must be a special relationship and wrongful act committed within that relationship - No trespass established; thus, no vicarious liability could arise. (Paras 43, 46)

Facts of the case:
The plaintiff claimed trespass against defendants for entering land under a Joint Venture Agreement, asserting lack of consent for occupation. The plaintiff, relying on a Power of Attorney, was found to lack standing to sue and the Power of Attorney was deemed invalid. (Paras 1-12)

Findings of Court:
The plaintiff lacked legal capacity to maintain the action, the Power of Attorney was invalid, and no trespass occurred. Claims against all defendants were dismissed. (Paras 52, 53)

Issues: Whether the plaintiff had the legal capacity to sue, the validity of the Power of Attorney, and whether trespass occurred on the land. (Paras 14, 21, 29)

Ratio Decidendi: The court held that a Power of Attorney must be valid and enforceable, and without it, the plaintiff could not claim possession or damages. The absence of evidence of possession and consent negated the trespass claim. (Paras 20, 34)

Result: Claims against all defendants dismissed.

Table of Content
1. allegations of trespass on jv land. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
2. plaintiff's legal capacity questioned. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20)
3. validity of power of attorney analyzed. (Para 21 , 22 , 24 , 26)
4. elements of trespass established. (Para 29 , 30 , 32 , 34 , 36)
5. damages for trespass claims evaluated. (Para 38 , 39 , 40 , 41)
6. vicarious liability principles discussed. (Para 43 , 44 , 46)
7. indemnity in third-party proceedings examined. (Para 48 , 49 , 50)
8. final conclusion and orders issued. (Para 52 , 53)
Ahmad Shahrir Mohd Salleh J:

Introduction

[1] This action arises from an alleged trespass upon a parcel of land held under GM 115, Lot No 5599, Mukim Kuala Lumpur, Wilayah Persekutuan Kuala Lumpur ("JV Land"). The plaintiff commenced this suit against the defendants alleging that the defendants had unlawfully entered and remained on the JV Land. The plaintiff contends that the alleged unlawful entry by the defendants unto the JV Land had deprived it of rights purportedly vested under a Joint Venture Agreement and a Power of Attorney, both dated 22 March 1995.

[2] In consequence, the plaintiff seeks several reliefs including damages for trespass, an order for vacant possession of the JV Land and an injunctive relief to restrain the purported further interference. In response to the claim, the 2nd defendant ("D2") initiated third-party proceedings against the 3rd defendant ("D3"). D2 seeks to be indemnified by D3 for any liability that may arise pursuant to the plaintiffs claim.

Background Facts

[3] Sometime in March 1995, the plaintiff entered into a Joint Venture Agreement ("JVA") with twenty-two registered proprietors of the JV Land including D3 for the purpose of undertaking a development project on the JV Land. On the same date, the twenty-two registered proprietors executed an Irrevocable Power of Attorney ("PA") in favour of the plaintiff which purported to vest in the plaintiff full authority to manage, develop and deal with the JV Land.

[4] Clause 4.2 of the JVA required the plaintiff to obtain all necessary regulatory approvals for the proposed development within twelve months from the date of the JVA with an allowable extension of six months. Clause 6.2 further stipulated that the development must be completed within thirty-six months from the date such approvals were obtained. Based on these terms, the development ought to have been completed by September 1999 at the latest. However, the JV Land has remained undeveloped and no construction was ever commenced by the plaintiff.

[5] Sometime in April or May of 2017, a majority of the landowners issued a notice purporting to terminate the JVA. Following the issuance of that notice, the plaintiff commenced arbitration proceedings against most of the landowners including D3. The arbitration concerned disputes relating to the alleged termination of the JVA and the purported continuing validity of the PA.

[6] The 1st defendant ("D1") acted as the developer of a project known as the "Cubic Botanical" development situated on the adjacent Lot 5598. D1 appointed the 4th defendant ("D4") as the main contractor for the said development. Subsequently, D4 appointed the 2nd defendant ("D2") as its subcontractor for building works comprised in the project.

[7] In August 2019, D2 entered into a tenancy agreement with D3 to lease a portion of the JV Land for a fixed term of twenty-four months commencing from 19 August 2019 until 18 August 2021 at a monthly rental of RM10,000.00. Under the terms of the tenancy, D2 was permitted to use the demised land for the construction of temporary office structures and workers' accommodation. It is alleged that one Dato' Low Boon An, who is a director of both D1 and D4, introduced D3 to D2 for the purpose of facilitating the tenancy arrangement.

[8] During the course of the tenancy, D2 sought to increase the area of the JV Land under lease. Following this, D2 agreed to pay D3 an additional

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top