HIGH COURT MALAYA IPOH
KERAJAAN MALAYSIA – Appellant
Versus
VEN-COAL RESOURCES SDN BHD – Respondent
| Table of Content |
|---|
| 1. contract awarded for building construction. (Para 1 , 1) |
| 2. delays caused by headmaster and unforeseen factors. (Para 2 , 8) |
| 3. piling work complications due to additional depths. (Para 3 , 21 , 22) |
| 4. request for extension of time (eot) denied. (Para 4 , 5 , 6) |
| 5. contract award and project delays. (Para 7) |
| 6. eot granted generally due to price increases. (Para 10 , 11 , 12) |
| 7. request for eot must consider prior extensions and reasons. (Para 13 , 16 , 19 , 38) |
| 8. stalemate due to headmaster's requirements. (Para 14 , 15) |
| 9. concurrent delays and extension evaluations. (Para 18 , 23) |
| 10. termination of contract evaluations. (Para 29 , 35) |
| 11. termination based on lack of diligent progress is contentious. (Para 30 , 31 , 32) |
| 12. counterclaim for payments arising from wrongful termination. (Para 56 , 57 , 58 , 59) |
[1] The plaintiff awarded to the defendant a contract to construct and complete 2 additional blocks of building for a school called Sekolah Kebangsaan Sungai Baharu, Kuala Kerian, Daerah Kuala Kerian, Perak ("the Project"). The contract entered into was the Standard Form PWD 203 (Rev. 10/83) Contract. The contract sum was for RM3,511,597.00. Under the contract the c
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.