2024 MarsdenLR 1682

HIGH COURT MALAYA KUALA LUMPUR
EASTMONT SDN BHD – Appellant
Versus
MEGA PLANNER JAYA SDN BHD – Respondent
[Suit No: WA-22C-51-06/2019]



Petitioner Advocates:Marcus Tan,Kwong and Chloe Fong Yin Kee ,Respondent Advocate: M Rajenthirakumar,Hiu Yeat Fong

The court upheld the Plaintiff's claims for outstanding payments while dismissing the Defendant's counterclaims for damages due to lack of evidence and timeliness, establishing principles of mutual termination and statutory limitations.

Headnote:(A) Companies Act 2016 - Section 540 - Liquidated damages - Contractual obligations in construction - Plaintiff's claim for RM7,230,492.14 for completed works upheld, while Defendant's counterclaim for liquidated damages dismissed due to failure to establish causation and timely claims - Claims for rectification costs also dismissed based on mutual termination terms and lack of evidence. (Paras 182, 183, 176, 177, 164, 165, 166)

(B) Limitation Act 1953 - Counterclaims - Defendant's counterclaim for liquidated damages barred by limitation as it was not raised within the statutory period following the issuance of the Certificate of Non-Completion. (Paras 140, 141)

Facts of the case:
The Plaintiff completed substructure works for serviced apartments; the Defendant counterclaimed for alleged delays and damages. The court found in favor of the Plaintiff on its claims while dismissing the Defendant's counterclaims as time-barred and unsubstantiated.

Findings of Court:
The court found the Plaintiff's claims valid and the Defendant's counterclaims unsupported by evidence, ruling that the mutual termination extinguished any claims for damages or rectification costs.

Issues: The main issues included the validity of the Final Statement of Account and the Defendant's claims for liquidated damages and rectification costs.

Ratio Decidendi: The court ruled that the Plaintiff proved its claims, while the Defendant failed to establish its counterclaims, particularly regarding causation for damages.

Result: Plaintiff's claim allowed; Defendant's counterclaim dismissed.

JUDGMENT

Aliza Sulaiman J:

Introduction

[1] This suit involves a protracted and bitter dispute over the Plaintiff's claim for outstanding sums for substructure works which were completed for the construction of serviced apartments in Setapak, Kuala Lumpur.

[2] The Defendant strongly resisted the Plaintiff's claim and brought a counterclaim of its own for among others, liquidated and ascertained damages ('LAD') for alleged delay in the completion of the substructure works and costs of rectification.

[3] After having considered the pleadings, oral and documentary evidence, written submissions and clarification by the learned counsels representing the parties, I had, on 30 August 2024 allowed the Plaintiff's claim in the sum of RM7,230,492.14 and dismissed the Defendant's counterclaim.

[4] The Defendant has appealed against part of my decision in:

(a) allowing the Plaintiff's claim in the sum of RM7,230,492.14 consisting of the following:

(i) RM4,850,814.42 as the balance payment for works done based on the Final Account dated 9 January 2019 with interest at the rate of 5% per annum from 10 June 2019 until full settlement;

(ii) RM193,792.80 as the balance payment for materials supplied;

(iii) RM189,999.92 as interest on the sum as stated in subparagraph (ii) above; and

(iv) RM1,995,885.00 as the balance payment for Variation Orders ('VO');

(b) dismissing the Defendant's counterclaim; and

(c) ordering that costs of RM80,000.00 be paid by the Defendant's contributory, Pelantar Segar (M) Sdn Bhd ('Pelantar Segar') to the Plaintiff.

[5] As the Plaintiff did not file a Notice of Appeal, these grounds of judgment shall deal with the issues which were decided in the Plaintiff's favor while the reasons for accepting the Defendant's submissions on the other issues will only be discussed briefly.

Agreed Facts

[6] The Statement of Agreed Facts for the trial are set out below.

[7] The Plaintiff is a company incorporated in Malaysia and having its business address at No 3, Jalan Medan Taiping 5, Medan Taiping, 34000 Taiping, Perak.

[8] The Defendant is similarly a company incorporated in Malaysia and having its registered address at No 8, Ground Floor, Jalan Bayu Tinggi 2A/KS6, Batu Unjur, 41200 Klang, Selangor and business address at No 15-1, 1st Floor, Jalan Remia 2/KS 6, 41200 Bandar Botanic Klang, Selangor.

[9] The Plaintiff and the Defendant are involved in the construction business.

[10] The Defendant was wound up pursuant to an order of the Shah Alam High Court ('SAHC') dated 14 May 2019 under the Winding Up Petition No BA-28NCC-97/2019 ('Petition 97') filed by Dakota Engineering Sdn Bhd ('Dakota').

[11] The Plaintiff obtained leave from the SAHC vide the Notice of Motion Post-Winding Up No BA-28PW-144-05/2023 on 10 July 2023 to proceed with this action against the Defendant.

[12] By the Letter of Award dated 3 August 2012 ('LoA'), the Defendant appointed the Plaintiff to carry out substructure works ('Works') for a project known as "Cadangan Pembangunan 2 Blok Pangsapuri Servis 16 Tingkat (412 Unit) di atas 7 Tingkat Podium dan Tingkat Bawah yang mengandungi 3 tingkat ruang perniagaan, 4 tingkat tempat letak kereta, 1 tingkat untuk kemudahan-kemudahan penduduk berserta unit kediaman di atas Lot 29094 (PT 7573 & 9462), Jalan Madrasah (Jalan 1/22A) Taman Melati, Mukim Setapak, Kuala Lumpur' ('Project') for the contract sum of RM26,000,000.00.

[13] On 5 December 2013, the Plaintiff and the Defendant mutually agreed to terminate the contract as stated in the Plaintiff's letter dated 5 December 2013 ('Termination Letter').

[14] The Defendant confirmed the mutual termination through its letter dated 9 December 2013 ('Defendant's 9 December 2013 Letter').

[15] On 18 December 2013, SJA Architect ('Architect') issued a Notice of Termination of Substructure Contract to the Plaintiff and the Defendant ('Notice of Termination') following a joint inspection conducted on 17 December 2013.

The Plaintiff's Case

[16] The Plaintiff contended that it has carried out the Works bas


Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top