HIGH COURT MALAYA KUALA LUMPUR
SCOMI TRANSIT PROJECTS SDN BHD – Appellant
Versus
PRASARANA MALAYSIA BERHAD – Respondent
[Originating Summons No: WA-24C-45-06/2016]
| Table of Content |
|---|
| 1. public transportation as a key to city livability. (Para 1 , 2) |
| 2. contractual obligations under the principal contract. (Para 3 , 4) |
| 3. role of performance bond in project contracts. (Para 5 , 6 , 7) |
| 4. validity of notice to terminate upon breach. (Para 8 , 9 , 10 , 18) |
| 5. adequacy of damages as a remedy. (Para 11 , 12 , 13 , 15) |
| 6. negotiation implication on enforcement. (Para 19 , 20 , 21) |
| 7. public interest associated with infrastructure projects. (Para 22 , 23 , 24 , 31) |
| 8. addresses the legal standards governing contract termination and the necessity of performance bonds. (Para 65) |
| 9. establishes that damages are a sufficient remedy, negating the need for an injunction. (Para 86 , 110 , 112 , 147) |
[1] Until people can travel by the "folding of space" as a science fiction would have us imagine, it is still the transportation from one place to another by roads, rails, by sea and air transport. A reliable and efficient mode of public transportation in a capital city is important both for commerce and industry, for work and play, for its people and for tourists as well. It is part of the factors that go into determining how livable a city is - convenience, comfort and connectivity.
[2] There has been for some time now the Kuala Lumpur Monorail connecting some important locations in the Kuala Lumpur city from the connecting hub of KL Sentral through the iconic Jalan Imbi/Jalan Bukit Bintang and even passing by the nostalgic Chow Kit. The experience of being sardine-packed with only standing space during rush hours is a common one. It would not be an exaggeration to say that what started off as a system of seamless connectivity of transport is now bursting at the seams. Hence the move to expand the number of trains by 12 more four-coach trains and also extending the number of stations.
Project
[3] The Defendant and Scomi Rail Bhd on 3 June 2011, entered into the Kuala Lumpur Monorail Fleet Expansion Project Contract ("Principal Contract") for the purposes of undertaking the engineering, procurement, construction and commissioning and provision of warranty ("Works") for the Kuala Lumpur Monorail Fleet Expansion Project ("the Project"). On the same day, the Defendant, Scomi Rail Bhd and the Plaintiff entered into a Novation Agreement where all the rights and liabilities of Scomi Rail Bhd under the Principal Contract were novated to the Plaintiff. Along the way the Plaintiff and the Defendant ("the Parties") entered into other agreements during the course of the Principal Contract with the aim of an orderly completion of the Works. The relevant agreements are the First Supplemental Agreement dated 16 April 2014 ("FSA") and the Second Supplemental Contract dated 15 April 2015 ("SSC"). The Principal Contract, the FSA and the SSC are collectively referred to as the "Contract".
Problem
[4] There were considerable delays in construction and commissioning of the Works. The Principal Contract being in June 2011, the Completion was supposed to be in July 2013. The Defendant has only delivered 5 out of 12 trains so far.
[5] The Defendant as Employer, issued a Notice of Termination dated 9 June 2016 to the Plaintiff as Contractor. It was a term of the Principal Contract in cl 4.2.1.2 that the agreed Performance Bond must be kept valid until the completion of the Works and the remedying of any defects.
[6] The Plaintiff did not renew the Performance Bond in spite of reminders by the Defendant. The Defendant by its letter of 25 April 2016 requested the Plaintiff to renew the Performance Bond, failing which it would exercise its right under cl 15.2 of the Principal Contract to terminate the Contract. However, instead of extending the Performance Bond which had expired on 25 April 2016, the Plaintiff wrote on 18 May 2016 to the Defendant requesting for a waiver of the requirement of the Performance Bond until 30 June 2016. This request was rejected by the Defendant pursuant to its letter dated 2 June 2016.
[7] The Defendants Notice of Termin
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.