2019 MarsdenLR 3682

HIGH COURT MALAYA KUALA LUMPUR
DB & B DESIGN SND BHD – Appellant
Versus
WAJAGAYA SDN BHD – Respondent
[Civil Suit No: WA-22C-87-10/2018]



Important Points

The burden of proof lies with the claimant, and claims must be substantiated with reliable evidence.

Subject

Civil Law - Contract Dispute

Headnote

This case revolves around a construction contract dispute where the Plaintiff sought damages for breach of a subcontract. The court found the Plaintiff's claims unproven owing to lack of testimonial evidence, dismissing the Plaintiff's claims and entering judgment for the Defendant's counterclaims. Critical issues included burden of proof, documentation adequacy, and recovery of liquidated damages. The final verdict dismissed the Plaintiff's action and ruled in favor of the Defendant.
Table of Content
1. overview of contract dispute and claims. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. mediation efforts and trial proceedings. (Para 7 , 8 , 9 , 10 , 12)
3. issues related to representation and adjournments. (Para 11 , 14)
4. court's decision to proceed ex-parte. (Para 16)
5. final judgment and counterclaim outcomes. (Para 18)

[1] This is an ex-parte trial decision of a construction contract dispute on wet trade works.

[2] The Plaintiff is a private limited company involved in the construction business and the main contractor for the project known as "Cadangan Tambahan Perubahan Serta Menukar Kegunaan Bangunan Daripada Rumah Kelab 6 Tingkat Sedia ada Kepada Pusat Perubatan Swasta 6 Tingkat Termasuk Tambahan 1 Tingkat Mezzanine Di Atas Lot No 20002, Seksyen 70, Jalan Travers, Bandar Kuala Lumpur, Wilayah Persekutuan For Cardiac Vascular Sentral (Kuala Lumpur) Sdn Bhd CVSKL-CP03" Main Building Works" ("Project").

[3] The Defendant is also a private limited company involved in the construction business and the sub contractor of the Plaintiff in respect of RC structural works, block works, plastering works, tiling works, and screening works of the Project ("Works") pursuant to a letter of award dated 5 September 2016 ("Sub Contract").

[4] The Plaintiff claimed that the Defendant in breach of the Sub Contract failed to execute and complete the Works diligently and timeously and as a result had to supplement labour force on behalf of the Defendant to complete the work. Eventually but prior to the completion of the Works, the Sub Contract was repudiated by the defendant in early 2017 and hence discharged.

[5] Consequently, the Plaintiff filed this Suit to recover damages amounting to RM1,193,836.81, including liquidated and ascertained damages of RM600,000.00, for delayed completion besides interest and costs.

[6] The Defendant in turn counterclaimed for the sum of RM2,955,856.00 (excluding GST) for original Sub Contract work and variation orders and general damages besides interest and costs.

Preliminary

[7] At the final pre-trial case management on 18 September 2019, the parties agreed to me mediating the Suit on both the claim and counterclaim, particularly their quantum without disqualification to try the Suit. The mediated quantum is without admission of liability and to be tried unless otherwise agreed.

[8] Consequently, the mediation was conducted on 30 September 2019 and 1 October 2019. During the course of the mediation, the parties only agreed to both the liability and quantum of the Defendant's counterclaim, for original work amounting to RM2,395,000.00 and variation orders amounting to RM1,075,000.00 respectively. The parties also agreed to both the liability and quantum of the Plaintiff's claim for back charges for supply of materials and labour until discharge of the Sub Contract amounting to RM460,000.00 which would be deducted from the counterclaim for original work and variation orders.

[9] The trial of the other remaining unresolved issues on the Plaintiff's claim which involved supplementation of labour force, purchase of materials on behalf of the Defendant, rectification work, overpayment and recovery of liquidated and ascertained damages for delayed completion of the Works was therefore to commence on 2 October 2019.

[10] Instead of commencing the trial, the parties in the morning of 2 October 2019 requested for a half day recess to attempt amicable settlement of the whole Suit through direct negotiations between themselves. I acceded to their request and granted a half day adjournment as requested. However in the afternoon of 2 October 2019, the parties informed me that they could not reach a settlement. Furthermore, the Plaintiff intimated to me that it lost confidence in its solicitors and had terminated their services. The Plaintiff hence sought for an adjournment of the trial to appoint new solicitors. I cautioned the Plaintiff that I was only willing to adjourn the trial for that day. Consequently, the trial would

1
2
3
4
5
6
7
8
9
10
11