HIGH COURT SABAH & SARAWAK KOTA KINABALU
KURNIA NIAGA – Appellant
Versus
KEMENTERIAN PERUMAHAN & KERAJAAN TEMPATAN & ANOR – Respondent
| Table of Content |
|---|
| 1. plaintiff's initial claim regarding contract terms and damages. (Para 1 , 2 , 4) |
| 2. defendants' responses and justifications for liquidated damages. (Para 3 , 11 , 12) |
| 3. details of the construction contract and the implications of the varied contract. (Para 5 , 10) |
| 4. determination of issues regarding extension of time and responsibilities. (Para 23) |
| 5. assessment of extension of time necessity under contract. (Para 24 , 25 , 28) |
| 6. court's reflection on previous case law and its applicability. (Para 32 , 33 , 34) |
| 7. final ruling regarding waiver of rights and judgment outcome. (Para 49 , 60) |
| 8. final determination on lad claims and the outcome based on contractual terms. (Para 52) |
[1] The Plaintiff, a building and construction contractor sued the Defendants arising from a contract dated 12 March 2008 it entered with the Defendants to carry out works known as "Merekabentuk, Membina dan Menyiapkan 1,000 Unit Rumah Pangsa 4-5 Tingkat dan Kerja-Kerja Yang Berkaitan Dengannya Bagi Program Perumahan Rakyat (PPR-Disewa) Di Batu 21/2, Jalan Bubul Lama, Semporna, Sabah" ("the Works") for the sum of RM68,686,000.00 ("the Contract Sum") subject to the terms and conditions therein
Kerajaan Malaysia (Jabatan Kerja Raya) v. Global Globe (M) Sdn Bhd
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.