HIGH COURT MALAYA KUALA LUMPUR
WRP ASIA PACIFIC SDN BHD – Appellant
Versus
NS BLUESCOPE LYSAGHT MALAYSIA SDN BHD – Respondent
[Originating Summon Nos: 24C-17-05/2015 & 24C-8-04/2015]
Key Points: - The adjudication decision can be set aside for denial of natural justice, excess of jurisdiction, improper procurement through fraud or bribery, or lack of independence/impartiality. (!) (!) (!) (!) - The court found that the adjudicator breached natural justice by engaging in unilateral/ex parte communications with one party without informing the other, and the adjudication decision was set aside for this reason. (!) (!) (!) (!) - The adjudicator’s competency was challenged under CIPAA 2012 and CIPAA Regulations 2014; the court reviewed the regulatory standards requiring at least seven years of working experience in the building/construction industry (in Malaysia or recognized fields) and other criteria (certificate in adjudication, not being undischarged bankrupt, no criminal convictions). The court ultimately accepted that the adjudicator met the competency standards as recognized by KLRCA, despite arguments to the contrary. (!) (!) (!) (!) (!) (!) (!) (!) - The court held that because of the bilateral nature of the adjudication process and the severity of procedural breaches, the decision could not be saved despite the adjudicator’s competency finding, and the decision was set aside for natural justice breaches. (!) (!) (!)
| Table of Content |
|---|
| 1. case background and parties' involvement (Para 1 , 2 , 5 , 6) |
| 2. grounds for setting aside adjudication decision (Para 15 , 19 , 24 , 50) |
| 3. importance of natural justice in adjudication (Para 21 , 22 , 102 , 118 , 122) |
| 4. competency criteria for adjudicators (Para 41 , 42 , 43 , 58 , 70) |
| 5. court's decision on the enforcement application (Para 120 , 123) |
A. Introduction
[1] These two cases which are heard together, relate to the same adjudication decision issued on 9 March 2015. NS Bluescope Lysaght Malaysia Sdn Bhd and Bluescope Lysaght (Malaysia) Sdn Bhd [Bluescope] were the Claimants in the adjudication claim while WRP Asia Pacific Sdn Bhd [WRP] was the Respondent. The adjudication decision was in Bluescopes favour. In Originating Summons No 24C-8-04/2015, Bluescope seeks to enforce the adjudication decision under s 28 of the Construction Industry Payment and Adjudication Act 2012 [CIPAA] whereas WRP seeks to set aside that same decision under s 15(a) and (d) of CIPAA under Originating Summons No 24C-17-05/2015.
[2] The parties have agreed that the enforcement of the adjudication decision will depend on the outcome of the application to set aside. Hence, the application to set aside was heard first.
[3] A total of 12 affidavits were filed by both parties:
[4] In its Amended Originating Summons, the orders sought by WRP include the following:
a. that the Adjudication Decision of Mr Noorfajri bin Ismail dated 9 March 2015 be stayed pending the final determination of this application;
b. a declaration that the Adjudication Decision is null and void because the Adjudicator did not meet the competency standard and criteria of an Adjudicator set by the Kuala Lumpur Regional Centre for Arbitration pursuant to s 32 of Construction Industry Payment and Adjudication Act 2012 and Regulation 4 of Construction Industry Payment & Adjudication Regulations 2014;
c. an order that the Adjudication Decision be set aside on the ground that it was given in excess of the Adjudicators jurisdiction and/or in breach of the rules of natural justice during the adjudication proceedings and/or in connection with the making of the Adjudication Decision.
B. The Construction Contract
[5] WRP engaged Bluescope to design, fabricate, deliver and install structural steel frames, steel roofing and walling etc at two factories, ie WRP Asia Pacific Sdn Bhd (F3 Project) and Grand Ten Holdings Sdn Bhd (G10 Project) in a project named "Cadangan Mendirikan Sebuah Kilang Sarung Tangan Getah 1½ Tingkat yang Mengandungi (i) Tingkat Bawah - Tempat Pengeluaran Pembungkusan (ii) Tingkat Mezzanine - Tempat Simpangan Di Atas PT 5759, HS(D) 7755, Jalan 3, Kawasan Perusahaan Bandar Baru Salak Tinggi" for RM6.58 million through a purchase order No 11135511000 DN dated 15 Jun 2012 [the construction contract].
[6] Differences arose between the parties over revisions to the roof design at the F3 project. Bluescope did not want to proceed with the revisions taking the position that the integrity of the steel structure would be affected. At the same time, WRP had not paid Bluescope on its Progress Claim No 7, the final progress claim. All this culminated with Bluescope suspending work and issuing several letters of demand. Despite this, WRP did not pay.
C. The Payment Dispute
[7] On 23 October 2014, Bluescope issued a payment claim under s 5 of CIPAA for the sum of RM5,241,731.02. This is the Payment Claim:
[8] WRP did not file any payment response. Under subs 6(4) of CIPAA, WRP is deemed to have disputed the payment claim.
[9] On or about 5 December 2014, Bluescope served a Notice of Adjudication together with supporting documents on WRP pursuant to subs 8(1). At the same time, Bluescope proposed a name as the Adjudicator. It was rejected by WRP.
[10] Consequently, the Director of KLRCA appointed Mr Noorfajri Bin Ismail as the Adjudicator under subs 9(2) on 23 December 2014. Both parties used consultants to represent them in the adjudication proceedings. WR
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.