2013 MarsdenLR 2988
HIGH COURT MALAYA KUANTAN
MOHAMED TAUFIQ TENG ABDULLAH & ORS – Appellant
Versus
MENTERI SAINS TEKNOLOGI DAN INOVASI MALAYSIA & ANOR; LYNAS CO.... – Respondent
[Application For Judicial Review No: 25NCVC-23-12-2012]
Important Points
Subject
Administrative Law - Judicial Review
Act Referred
Court Rules: S.O 53 r 3(1), S.O 53 r 3(5), S.O 53 r 8(1), S.O 15
Headnote
(B) Intervention - Criteria for intervention in judicial review - Proposed interveners demonstrated a direct interest in the decision and were allowed to participate as parties in the proceedings. (Paras 6-10)
Facts of the case:
A judicial review application was filed challenging decisions associated with the Temporary Operating License granted to a project. The applicants alleged bias and jurisdictional excess by a minister.
Findings of Court:
The Court recognized the interveners as proper parties given their direct interest and potential adverse impact from the judicial review outcome.
Issues: The court addressed whether the proposed interveners could join the judicial review proceedings based on their direct interest.
Ratio Decidendi: The court held that the proposed interveners fulfilled the criteria for intervention due to their demonstrated direct interest in the outcome, notwithstanding existing procedural contentions against being deemed parties.
Result: Application allowed.
| Table of Content |
|---|
| 1. judicial review application filed for tol. (Para 1) |
| 2. court's final decision to allow intervention. (Para 2 , 8) |
| 3. court's consideration of timely hearing and objections. (Para 3 , 6) |
| 4. arguments regarding intervention rights of proposed interveners. (Para 4 , 5) |
| 5. court's determination on the inclusion of interveners. (Para 7 , 10) |
[1] The Applicants in this case had on 3rd December 2012 filed an ex-parte application for leave to make an application for Judicial Review under O 53 r 3(1) of the Rules 2012.
In the leave application, the Applicants prayed for the following:-
a. For a leave to be granted to apply for an Order of Certiorari for the purpose of quashing the decision of the above named 1st Respondent and/or the 2nd Respondent in issuing the Temporary Operating License ("T.O.L") on 3 September 2012 in favour of Lynas Advanced Materials Plant ("LAMP");
b. For a Declaration that the TOL granted in invalid and void;
c. For a leave to be granted to apply for an Order of Certiorari for the purpose of setting aside and quash the decision off the 2nd Respondent in issuing the Temporary Operating License ("TOL") on 3 September 2012 in favour of Lynas Advanced Materials Plant ("LAMP") , despite the current and on-going Judicial Review proceedings at the Kuantan High Court in the case of Kuantan High Court Judicial Review No. 25NCVC-17-7-2012 and No. 25NCVC-18-7-2012 challenging the decision of the 2nd Respondent dated 3 September 2012 that has been affirmed subject to additional condition by the 1st Respondent on 13 June 2012.
d. For a leave to be granted for an Order of Certiorari for the purpose of setting aside and quashing the decision of the above named 1st Respondent on 13 June 2012 in disallowing/dismissing the appeal of Ismail Bin Abu Bakar, Abujavalli A/P Raman and Tan Ah Meng with the imposition of two (2) additional conditions which further reaffirms the decision of the 2nd Respondent on 30 January 2012 granting the TOL to Lynas Malaysia Sdn Bhd, subject to five (5) operational conditions towards Lynas Advanced Material Plants ("LAMP") at Gebeng, Kuantan.
e. For a leave to be granted for a Prohibitory Order prohibiting the 1st Respondent from issuing any license; temporary or permanent to Lynas Malaysia Sdn Bhd except and until:-
(i) Lynas Malaysia Sdn Bhd provide a Detailed Environmental Impact Assessment Report ("DEIA") to the 2nd Respondent and subject to the approval of DEIA by the Director of the Environmental ("DOE");
(ii) Lynas Malaysia Sdn Bhd to provide a new Radiological Impact Assessment Report to the 2nd Respondent for its approval; and
(iii) Lynas Malaysia Sdn Bhd to provide new proposals for Safety Case for Radioactive Waste Disposal ("SCRWD") and Radioactive Waste Management Plan ("RWMP") to the 2nd Respondent for its approval made in pursuant to the proposals by the International Atomic Energy Agency in its Report dated 30 June 2011.
f. That the TOL be stayed pursuant to O 53 r 3(5) of the Rules 2012 and/or inherent jurisdiction of this Honourable Court pending the disposal of this proceeding;
g. For a Declaration that the Minister had exhibited a real likelihood of bias in favour of the LAMP project and therefore ought not to have adjudicated any appeals of the decision of the AELB in granting the TOL to the LAMP Project pursuant to s 32 AELA 1984;
h. For a Declaration that the Minister had acted in excess of jurisdiction and the ouster clause in s 32(5) of the AELA 1984 is of no effect;
i. Any extension of time to be granted (if need be) to commence this Judicial Review proceeding in accordance with the Rules of High 1980;
j. Costs;
k. Any other additional reliefs deems fit and proper by this Honorable Court.
Decision
[2] The application to be determined by this Honorable Court is:
The Application By The Proposes Interveners' To Intervene And To Add As A Party In The Judicial Review Proceedings That Is Encl 6
The issue in this