HIGH COURT MALAYA SHAH ALAM
OOI CHENG HUAT @ OOI PENG HUAT & ORS – Appellant
Versus
SIME DARBY PROPERTY BERHAD & OTHER CASES – Respondent
[Civil Suit Nos: BA-22C-43-10/2017 BA-22C-44-10/2017 BA-22C-45-10/2017 BA-22C-46-10/2017 BA-22C-47-10/2017 & BA-22C-49-11/2018]



Important Points

Court affirmed that housing developers must adhere to statutory obligations regarding construction quality and materials, ensuring purchaser protection under the Housing Development Act.

Subject

Civil Law - Contract Law

Act Referred

Headnote

(A) Housing Development (Control and Licensing) Act 1966 - Breach of Sale and Purchase Agreements (SPAs) - Plaintiffs alleged defects in six bungalows constructed by Defendant - Court held that Defendant breached obligations under Housing Developer's Obligation (Materials) and (Good Workmanship) - Relevant clauses interpreted to protect purchasers' rights against developers. (Paras 1-127)

(B) Evidence - Burden of proof - Plaintiffs must prove existence of defects and causation on balance of probabilities - Court emphasized that expert evidence is not always necessary for determining defects. (Paras 59-63)

Facts of the case:
Plaintiffs filed six suits against Defendant for breach of SPAs regarding construction defects in bungalows, alleging defects and forgery in defect rectification forms. (Paras 1-16)

Findings of Court:
Plaintiffs proved defects due to Defendant's failure to comply with statutory obligations; awarded damages for rectification costs and defects. (Paras 72-73, 105-109)

Issues: Did Defendant breach SPAs? What is the extent of liability for defects? (Paras 21-22)

Ratio Decidendi: Court ruled on interpretation of statutory obligations and the necessity of expert evidence in proving defects; emphasized that the Developer's obligations cannot be circumvented by reliance on the Home Owners Manual. (Paras 45-46, 91-92)

Result: Plaintiffs' claims allowed; Defendant ordered to pay damages and costs. (Paras 124-126)

Petitioner Advocates:Colin Andrew Pereira,Gary Wong Kin Wai ,Respondent Advocate: Rohan Arasoo Jeyabalah,Amy Hiew Kar Yi,Pan Yan Teng

JUDGMENT

(After Trial)

Wong Kian Kheong J:

A. Introduction

[1] This judgment arises from a joint trial (Trial) of the above six suits (6 Suits) filed by purchasers (Plaintiffs) of six bungalows built and sold (6 Bungalows) by the defendant company (Defendant), a housing developer.

[2] In these 6 Suits, the Plaintiffs claimed that the Defendant had breached various provisions of six Sale and Purchase Agreements of the 6 Bungalows (6 SPAs) entered into between the Plaintiffs and Defendant [Alleged Defendant's Breaches (6 SPAs)]. The Alleged Defendant's Breaches (6 SPAs) concern novel legal issues regarding certain clauses in the 6 SPAs.

B. Background

[3] The 6 Suits are as follows:

(1) suit No BA-22C-43-10/2017 (Suit No 43) had been filed by the plaintiffs [Plaintiffs (Suit No 43)] against the Defendant with regard to a two-storey bungalow with a basement [Bungalow (Suit No. 43)] which was-

(a) built on land held Grant 174772, Lot 70087, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 1 December 2010 [SPA (Suit No 43)];

(2) suit No BA-22C-44-10/2017 (Suit No 44) was filed by the plaintiff company [Plaintiff (Suit No 44)] against the Defendant in respect of a two-storey bungalow with a basement [Bungalow (Suit No. 44) ] which was-

(a) built on land held Grant 174763, Lot 70078, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 18 April 2012 [SPA (Suit No 44)];

(3) suit No BA-22C-45-10/2017 (Suit No 45) had been filed by the plaintiff [Plaintiff (Suit No 45)] against the Defendant in respect of a two-storey bungalow with a basement [Bungalow (Suit No 45)] which was-

(a) built on land held Grant 174760, Lot 70075, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 1 December 2010 [SPA (Suit No 45)];

(4) suit No BA-22C-46-10/2017 (Suit No 46) was filed by the plaintiff [Plaintiff (Suit No 46)] against the Defendant in respect of a two- storey bungalow with a basement [Bungalow (Suit No 46)] which was-

(a) built on land held Grant 174770, Lot 70085, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 22 April 2013 [SPA (Suit No 46)];

(5) suit No BA-22C-47-10/2017 (Suit No 47) had been filed by the plaintiffs [Plaintiffs (Suit No 47)] against the Defendant in respect of a two-storey bungalow with a basement [Bungalow (Suit No 47)] which was-

(a) built on land held Grant 174771, Lot 70086, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 16 April 2012 [SPA (Suit No 47)]; and

(6) suit No BA-22C-49-11/2018 (Suit No 49) was filed by the plaintiffs [Plaintiffs (Suit No 49)] against the Defendant in respect of a two- storey bungalow with a basement [Bungalow (Suit No 49)] which was-

(a) built on land held Grant 174750, Lot 70066, Mukim Damansara, Petaling District, Selangor; and

(b) sold pursuant to a SPA dated 28 April 2015 [SPA (Suit No 49)].

[4] With regard to SPA (Suit No 43), SPA (Suit No 44), SPA (Suit No 45) and SPA (Suit No 47) [collectively referred to in this judgment as "4 SPAs (Suits No 43 to 45 and 47)"]:

(1) at the time of the execution of 4 SPAs (Suits No 43 to 45 and 47), Bungalow (Suit No 43), Bungalow (Suit No 44), Bungalow (Suit No. 45) and Bungalow (Suit No 47) [collectively referred to in this judgment as "4 Bungalows (Suits No 43 to 45 and 47)"] were still under construction by the Defendant; and

(2) the 4 SPAs (Suits No 43 to 45 and 47) were based on the "statutory' SPA (Statutory SPA) prescribed in Schedule G (Schedule G) to Housing Development (Control and Licensing) Regulations 1989 (HDR).

[5] At the time of the execution of SPA (Suit No 46) and SPA (Suit No 49) [collectively referred to in this judgment as "2 SPAs (Suits No 46 and 49)"], the construction of Bungalow (Suit No 46) and Bungalow (Suit No 49) [collectively referred to in this judgment as "2 Bungalows (Suits No 46 and 49)"] had already been completed.

[6] Section 6.01 in the 2 SPAs (Suits No 46 and 49) [Section 6.01 (Sui