FEDERAL COURT PUTRAJAYA
USIMA SDN BHD – Appellant
Versus
LEE HOR FONG – Respondent
| Table of Content |
|---|
| 1. determination of contractual obligations and interpretations. (Para 8 , 9 , 10) |
[8] The significance of these two dates may be gleaned from the judgment of the learned High Court Judge found at p 16 of his judgment:
"... although the letter of termination was dated on the 13th January 2003 and received by the Plaintiff on the 20th February 2003, there were ample evidence to show that the Plaintiff had abandoned the construction site as early as mid-December 2002. This is evident by the appointment of the third parties to complete the uncompleted contract works."
[9] The learned High Court Judge found that LHF had abandoned the contract. At p 17 of the judgment, His Lordship opined:
In the circumstances, the Court was of the view that the defendant was not in breach of the contract when it terminated it and therefore was entitled to appoint other contractors to finish the uncompleted contract works. The Court was also of the view that since the defendant was at all material time the main contractor of the contract work and it suffices that the issuance of the memo to the plaintiff were indicative that the plaintiff had abandoned the construction site."
[10] Being over
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.