2000 MarsdenLR 1858
RICHARD MALANJUM
HIGHCEED CORPORATION SDN BHD – Appellant
Versus
WARISAN HARTA SABAH SDN BHD – Respondent
Important Points
Subject
Contract Law - Construction Contract
Act Referred
Headnote
Counsel for the Defendants:Pn. Jainab Ahmad, Messrs Jainab & Associates, Advocates & Solicitors
| Table of Content |
|---|
| 1. court concludes on the lack of triable issues. (Para 8) |
A. Introduction:
By way of Summons in Chambers dated 1st December 1998 the Plaintiff is applying under Order 14(1) of the Rules of the High Court 1980 for the following relief, to wit,:
"(a) A declaration that the First Defendant has wrongfully repudiated the Building Contract dated 17 January 1998 and has thereby prevented the Plaintiff from repaying the advance payment of RM5.0 million in accordance with the terms of the advance payment and/or satisfying the terms of the Insurance Guarantee Against Advance Payment (For Works) issued under Policy No. N-7-97-TA-000002;
(b) A declaration that the First Defendant has wrongfully repudiated the Building Contract dated 17 January 1998 and has thereby prevented the Plaintiff from completing its performance of the Building Contract;
(c) Damages to be assessed; and
(d) Costs."
In support of the application the Plaintiff filed an affidavit in support affirmed by Mr. Lim Ching On on 01.12.98 (Lim's 1st Affidavit).
The Defendant is objecting to the application and has therefore filed an affidavit in opposition affirmed by Datuk Hj. Matiasin Surai and filed on 06.04.99 (Matiasin's 1st Affidavit). A further affidavit was also filed on 28.04.99 (Matiasin's 2nd Affidavit).
Subsequently, the Plaintiff filed an affidavit in reply affirmed by Mr. Lim Ching On on 20th April 1999 (Lim's Affidavit in reply).
B. The Relevant And Undisputed Facts:
By a letter of Award dated 12.08.97 ('Letter of Award') the 1st Defendant appointed the Plaintiff as a contractor to carry out the construction of a commercial building complex on a parcel of land situated in Kota Kinabalu under PT2 of Title Deed No. TL 017533881 for a contract sum of RM175 millions. The project was described as a "Proposed Office Development Consist of 12, 8 & 13 Storey For Banking, Office And Restaurant With 1 Level Sub-Basement And 1 Level Basement Car Park And 4 Levels Elevated Car Park (With Subsidiary (Strata) Titles To Be Applied For)" (hereinafter referred to as 'the Project'). The period of completion was scheduled for 24 months from the date of possession of site. Subsequently, a Building Contract was signed on 17.01.98 ('the Building Contract').
There was another agreement signed between the Plaintiff and the 1st Defendant called the Marketing Agreement dated 13.08.97 ('Marketing Agreement').
Pursuant to the Letter of Award the Plaintiff procured a Performance Bond for RM8.75 million in favour of the 1st Defendant issued by the 2nd Defendant under Policy No. N-7-97-TA-000001 dated 31.12.97 ('the Performance Bond').
And in approving an advance of RM5 millions ('the Advance') to the Plaintiff the 1st Defendant stipulated conditions, inter alia,
"(a) the Special Provisions to the Conditions of Contract (additional terms and conditions) as per Attachment I; and
(b) the provision of a bank guarantee against advance payment as per Proforma attached."
And paragraphs 7 and 8 of Lim's 1st Affidavit described the mode of recouping the Advance and the termination of the bank guarantee as thus:
" 7. The advance payment of RM5.0 million was to be recouped in the manner provided in the Special Provisions to the Conditions of Contract (additional terms and conditions) as per Attachment I, namely when the cumulative total value of the builder's work executed and certified (including the amount certified for materials on site) in the progress payment certificates reached twenty five (25) percent of the total contract value of builder's work; by way of a fixed percentage deduction from the total certified value of the builder's work executed (including the amount certified for materials on site) during the period covered by Progress Payment Certificates, in all the subsequent progress payment certificates on the basis that the advance payment made shall be fully recovered in the progress payment certificate in which the cumulative total certified value of builder's