SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 MarsdenLR 2871

FEDERAL COURT PUTRAJAYA
OBATA-AMBAK HOLDINGS SDN BHD – Appellant
Versus
PREMA BONANZA SDN BHD & OTHER APPEALS – Respondent
[Civil Appeal Nos: 02(i)-70-08-2022(W) 02(i)-71-08-2022(W) 02(i)-72-08- 2022(W) 02(i)-74-08-2022(W) & 01-(f)-1-01-2023(B)]



Petitioner Advocates:Low Joo Hean,Chan Kim Weng,Kuan Jia Yin ,Respondent Advocate: Lai Chee Hoe,Ooi Xin Yi,Angeline Ang Mei Fong

The court ruled that extensions under reg 11(3) of the HDR are invalid as ultra vires, affirming that LAD claims are time-barred beyond the six-year limitation period.

Headnote:(A) Housing Development (Control and Licensing) Act 1966 - Housing Development (Control and Licensing) Regulations 1989 - Regulation 11(3) - Liquidated Ascertained Damages (LAD) - Appeals concerning LAD claims due to extension of completion periods - The court ruled that extensions granted under reg 11(3) are invalid following the precedent set in Ang Ming Lee, which declared the regulation ultra vires. (Paras 2, 60, 68, 78, 102)

(B) Limitation Act 1953 - The court held that claims for LAD are time-barred as they were filed beyond the six-year limitation period from the date of breach of contract. (Paras 15, 34, 102)

Facts of the case:
The appeals involve claims for LAD by purchasers against developers for delays in delivering vacant possession of properties, with disputes arising over the validity of extended completion periods granted prior to execution of Sale and Purchase Agreements (SPAs). (Paras 4, 7, 20)

Findings of Court:
The court affirmed that the extension of time granted by the Housing Controller was invalid, and the claims for LAD were barred by limitation, given the purchasers' acceptance of the amended terms in the SPAs. (Paras 36, 102)

Issues: The main issues were the validity of the extended completion periods and the applicability of the limitation period for claims of LAD. (Paras 1, 19)

Ratio Decidendi: The court emphasized the binding nature of the Ang Ming Lee decision, declaring reg 11(3) ultra vires and reiterating that the limitation period for LAD claims commences from the date of breach. (Paras 60, 102)

Result: Appeals dismissed and the decisions of the High Court reinstated.

JUDGMENT

Hasnah Mohammed Hashim FCJ:

Introduction

[1] There are five appeals which were heard together, given the commonality of issues in the questions of law raised for our determination. One appeal was filed by the purchaser of the condominium units, The Sentral Residences. The other appeals are appeals filed by the developers of the projects, Prema Bonanza Sdn Bhd (Prema) and Sri Damansara Sdn Bhd (Sri Damansara). The appeals were heard together despite there being different parties involved. We heard oral submissions by all learned counsel representing the respective parties and at the end of those submissions, we indicated that we needed time to consider the respective submissions. We have now reached our decision and what follows below are our deliberations on the issues raised and our reasons as to why we have so decided.

[2] The central issue in all the appeals concerns the payment of Liquidated Ascertained Damages (LAD) as a result of this court's decision in Ang Ming Lee & Ors v. Menteri Kesejahteraan Bandar Perumahan Dan Kerajaan Tempatan & Anor And Other Appeals; 2019 MarsdenLR 2737 ; ; [2019] 8 AMR 297 (Ang Ming Lee) declaring that reg 11(3) of the Housing Development (Control and Licensing) Regulations 1989 (HDR) is ultra vires the parent Act.

Appeal No: 02(i)-70-08-2022(W) (Appeal No. 70) & 02(i)-71-08/2022(W) (Appeal No. 71)

Obata-Ambak Holdings Sdn Bhd (Obata) v. Prema Bonanza Sdn Bhd (Prema)

[3] Both appeals have identical issues, with similar facts, and arose from the same development project. Appeal No. 70 is an appeal by Obata against the decision of the court of Appeal dismissing the appeal by Obata against the High court's decision which allowed Prema's application under O 14A Rules of 2012 (ROC). Whereas Appeal No. 71 is an appeal by Obata against the court of Appeal's decision which dismissed Obata's application for Summary Judgment under O 14 ROC 2012.

[4] The Appellant, Obata, is the purchaser and owner of a condominium known as The Sentral Residences (the Project). The Respondent, Prema, is the developer of the Project. The Project comprises 2 towers of service apartments and was governed by the Housing Development (Control and Licensing) Act 1966 (HDA) and the HDR. Thus, the agreement was to be executed with potential purchasers as prescribed under Schedule H of the HDR, whereby the time for delivery of vacant possession and completion of common facilities is 36 months.

[5] However, due to the magnitude and the peculiarity of the bespoke design of the Project, Prema applied for modification of the prescribed agreement to vary the prescribed completion period for the Project from thirty-six (36) months to fifty-four (54) months pursuant to reg 11(3) HDR. The Extension of Time (EOT) was granted by the Controller of Housing (the Controller) on 16 December 2010, two (2) years before the execution of the SPA with the purchasers of the Project. Prema obtained the EOT to extend the time period for delivery of vacant possession and completion of common facilities from 36 months to 54 months. The amended approved provisions are as reflected in cls 25 and 27 of the Sale and Purchase Agreements (SPA). It was only after procuring the approval of the EOT and the amended clauses in the SPA that Prema executed the SPAs with its purchasers.

[6] Obata entered into the SPAs with the approved EOT on various dates which formed the subject matter before the court, namely:

(i) SPA dated 24 July 2012 (Suit 301);

(ii) SPA dated 28 October 2013 (Suit 303); and

(iii) SPA dated 11 July 2012 and 18 July 2012 (Suit 305) − the present appeals before us.

[7] After the Federal court's decision of Ang Ming Lee, Obata commenced proceedings against Prema for the following reliefs:

i. a declaration that any letters given for extension of time pursuant to reg 11(3) of the HDR to deliver vacant possession of the property to the plaintiff and the completion of the common facilities from 36 months to 54 months were inconsistent with the decision o

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top