SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1994 MarsdenLR 538

SUPREME COURT IPOH
AYER HITAM TIN DREDGING MALAYSIA BHD – Appellant
Versus
YC CHIN ENTERPRISES SDN BHD – Respondent
[Civil Appeal No: 03-12-93]



Petitioner Advocates:Su Tiang Joo,Teh Meng Teck ,Respondent Advocate: RR Sethu,Khoo Eng Ching

JUDGMENT

Edgar Joseph Jr SCJ:

[1] The primary issue which arises for decision in this appeal is whether there was a concluded contract between the appellant as employer and the respondent as contractor, to construct and develop low-cost houses and shophouses for the appellant's workers, in the Mukim of Dengkil, the District of Sepang, State of Selangor.

[2] The appellant, who was the defendant in the Court below, is a public limited company incorporated in Malaysia with its registered office at 16, Jalan Tangsi, Kuala Lumpur.

[3] The respondent, who was the plaintiff in the Court below, is a private limited company incorporated in Malaysia with its principal place of business at 448, Jalan Pudu, Kuala Lumpur, carrying on the business of building and general contractors.

[4] It would be more convenient to refer to the appellant and the respondent as the defendant and the plaintiff respectively. The record provided shows that in March 1981, the plaintiff had entered into negotiations with a third party Malaysia Mining Corporation Berhad ("MMCB"), a majority shareholder of the defendant, to develop and construct low cost houses and shophouses for the defendant's workers hereinbefore mentioned ("the project"). So far as the defendant was concerned, the project was non-profitable. By September 1984, the defendant's board of directors being agreeable to the plaintiffs proposals, the secretary of the defendant wrote a letter dated 19 September 1984 addressed to the plaintiff ("the letter of 19 September 1984") in the following terms:

Dear Sirs,

Ayer Hitam Tin Dredging Malaysia Berhad (AHTB) Workers Housing Scheme

We refer to the above subject and are pleased to advise that your proposals for the implementation of the housing scheme are agreeable to the Board of Directors of the Company, subject to the following terms and conditions:

(i) that the project shall be on a turnkey basis;

(ii) that the design and selling prices of the individual units shall be as approved by the Jawatankuasa Tetap Kebajikan Pekerja- Pekerja Ladang dan Lombong, Selangor;

(iii) that YC Chin Enterprises shall arrange for end financing of the project;

(iv) payments to YC Chin Enterprises shall be made at stages of completion in accordance with the payment schedule as agreed between the end financier and YC Chin Enterprises and that AHTD (the plaintiff) shall not be liable for any progress payment;

(v) the filling and levelling of the site shall be carried out by YC Chin Enterprises for which AHTD undertakes to pay a sum not exceeding RM300,000 towards the cost of this work;

(vi) that the above terms and conditions be constituted in the form of an agreement between YC Chin Enterprises and AHTD and that appropriate indemnity clauses in favour of AHTD in respect of material defects in site work, foundation and buildings in the project be incorporated in the said agreement.

A copy of the draft agreement will be forwarded to you in due course for your perusal.

We trust that the above are in order and should you agree to the above terms and conditions, kindly sign the duplicate copy of this letter and return to us as soon as possible.

Yours faithfully

Ayer Hitam Tin Dredging Malaysia Berhad

Sgd.

Secretary

[5] In reliance upon the letter of 19 September 1984, the plaintiff had proceeded to make arrangements for end financing for the project and had also commenced preliminary works on the site, for which purpose, architects, engineers and surveyors were appointed. This, they did, although no formal agreement in writing had been executed but in the confident belief that the letter of 19 September 1984 constituted a binding contract.

[6] However, although a copy of the draft agreement referred to in the letter of 19 September 1984 was, in due course, forwarded to the plaintiff for their approval, no such approval was forthcoming, much less any agreement signed, and as late as November to December 1986, the contemporary correspondence passing between the plaintiff and MMCB indicated clearly th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top