SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1976 MarsdenLR 26

FEDERAL COURT PENANG
PUBLIC TEXTILES BERHAD – Appellant
Versus
LEMBAGA LETRIK NEGARA – Respondent
[Civil Appeal No: 177 Of 1974]



Petitioner Advocates:Lim Kean Chye ,Respondent Advocate: Chin Yew Meng

JUDGMENT

Raja Azlan Shah FJ:

1

[1] The respondents ("the Board") had contracted to supply electricity to the appellants. By mistake, it had considerably undercharged the appellants to the amount of $84,624.01 and successfully claimed that amount from them. The learned trial judge held that the Board was not estopped from claiming that amount although the appellants had utilised the accounts rendered by the Board forthe purpose of costing their products. To have admitted the estoppel, so the learned judge held, would have had the effect of nullifying the statutory provisions of the Electricity Act, 1949 (Revised - 1973).

[2] This is an appeal against that decision.

[3] Before stating the facts on which this appeal turns, and the contentions of counsel, it seems to be convenient to refer to the relevant statutory provisions of the Electricity Act, 1949 (Revised - 1973) and the Electricity (Board Supplies) Rules, 1949, (L.N. 515/49; amended L.N. 235/64).

[4] The Board is a corporate body constituted under s 3 of the Act, and is accordingly under a statutory duty to secure the supply of energy at reasonable prices (section 15), to enter into contracts with any person upon such terms and conditions as it may determine (section 16), and to fix the prices to be charged which shall be in accordance with such tariffs as may, from time to time, be fixed by regulations made under s 89 (section 21(1)). The Board is under the control and supervision of the Minister who appoints the members (s 5) and is required to make annual reports and returns and a copy thereof to be transmitted to the Minister as well as to be laid before the Dewan Raayat- (sections 25, 27). Although the Board has a free hand to enter into contracts for the supply of energy, the rates which it can make and exact are strictly limited, and must be in exact accordance with the provisions of the First Schedule - "contracts at scheduled rates" (rule 29). It has power to amend the schedules and to make charges for energy supplied in different places or districts on different systems, or while maintaining the same system, at different rates (rule 4(5)), but that powercannot override the statutory duty of the Board not to show undue preference or undue discrimination as between consumers similarly situated (section 21(2)). Monthly bills are rendered by the Board to the consumer which must be paid within 7 days of presentation, failing which the installation may be disconnected without further notice (rule 8(1)).

[5] The appellants during the material times carried on a textile business in Butterworth, Province Wellesley. They had entered into a contract with the Board tobuy from it electricity energy at scheduled rates - at Tariff E - Fixed Block Industrial Tariff. Because at that time a 2-way summation system was not available and because of the urgency of the appellants' need, a 3-way summation system was installed. Since the factory is using 2 power transformers, a multiplication factor of 3/2 is required to ascertain the actual units consumed. If a 2-way summation metering system is used, then a multiplication scale is not required, and a direct reading would showthe actual units consumed. Due to an error of the Board's servants, the correct multiplication factor was not applied, thus the appellants were not rendered proper bills from the commencement of the contract ie December 16, 1970, until the omission was discovered on April 29, 1972. At that time an engineer of the Board was taking stock of summation current transformers in order to assess its requirements for the next annual period and he called in these forms as well as the requisitions. It was then discovered that there was discrepancy between Form LLN 98 and the particular requisition form. The former, which is normally used to advise meter readers as to what factor to use on the meter reading, showed a 2-day summation metering system, whereas the latter showed a 3-way system. Of course, the former is not correct. A ju

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top