1977 MarsdenLR 168

JUDGMENT

Lee Hun Hoe CJ (Borneo):

These appeals arise consequent upon the decision of the learned Judge in respect of a consolidated action of two civil suits, namely, CS No. 25/72 ("the first suit") and CS No. 71/72 ("the second suit"). Both suits are concerned with breaches of contract. Sim Siok Eng has appealed against the decision of the learned Judge in respect of both suits and the Government of Malaysia has cross-appealed against the decision in "the first suit." For convenience, Sim Siok Eng will be referred to as the appellant and the Government of Malaysia as respondent.

Appellant was a well-known local contractor and had tendered and completed successfully about twenty major projects to the satisfaction of the Government. In January 1969 Government called for tenders for the construction of the Sibu Infantry Battalion Complex which covered nearly 200 acres of land at 14 Mile Oya Road, Sibu, Sarawak. Fourteen contractors bid for the contract. Sim's tender for $3,930,000 was accepted. The contract was signed on 6 March 1969 and was to be completed within eighteen months. After signing the contract appellant discovered that his office had made a serious error of calculation involving $1,300,000. Instead of four units to one block his office calculated the tender on the basis of two units to one block. In other words, instead of 320 units his office calculated 160 units. Despite this appellant did not ask to be released from the contract. He felt that it would still be possible to make a small profit. He was more concerned with preserving his reputation as a good contractor, During the course of the contract two extensions totalling slightly more than four months were granted for the completion of the contract. Due to these extensions the contract sum was, therefore, raised to $4,002,532.54. The extensions took the completion date to 28 December 1970. Under cl. 4 of the Conditions of Contract appellant was obliged to supply materials and labour.

To finance the contract Sim managed to get the Hock Hua Bank to grant him clear overdraft facilities up to $300,000 and Letters of Credit amounting to $800,000. In 1970 he found difficulty in obtaining building materials to complete the work so he saw the Director of Public Works Department, Sarawak. A meeting was called on 9 October 1970. Those present were the Director of Public Works Department (Ng Siak Kee), the Assistant Director of Armed Forces Works (Law Kiat Howe), the Divisional Engineer (Michael Parker) and the appellant. As a result the respondent orally agreed to supply the appellant with certain building materials the cost thereof to be deducted from the payment due to the appellant. From then on whenever the appellant wanted such building materials he would just write to the Divisional Engineer. One of the materials was waterproof plywood for which an order was placed for 25,000 pieces. The first shipment of 400 pieces and second shipment of 7,000 pieces reached the site. About 3,400 pieces were used, Then the Anti Corruption Agency seized the plywood and locked them in the store and asked appellant not to use them. Later, the Anti Corruption Agency took them away. The Director of Public Works also wrote to appellant advising him not to use them. No reason was given. By December 1970 a large percentage of the external part of the project had been completed. Without plywood it was not possible for appellant to instal internal partitioning.

Twenty-three progress payments totalling $3,091,497.75 were made. The last progress payment made on 2 November 1971 was based on assessment made by respondent's representative dated 22 October 1970. No building materials were supplied after seizure of plywood by the Anti Corruption Agency. Consequently, appellant stopped work on 4 April 1971. After he stopped work his contract was terminated, purportedly under cl. 34(a)(ii) on 28 April 1971. The Government called for another tender and contractor Alex Tong completed the work