SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1988 MarsdenLR 1235

SUPREME COURT, KUALA LUMPUR

SALLEH ABAS LP, ABDUL HAMID CJ (MALAYA), LEE HUN HOE CJ (BORNEO)

HOO SEE SEN
versus
PUBLIC BANK BHD

CIVIL APPEAL NO. 335 OF 1987

Decided On : 03-17-88

Advocates:
For the appellants - Ngeow Yin Ngee; M/s. Ngeow & Maurice Gomes
For the 1st respondent - Suhendran Sockanathan; M/s. Chooi & Co
For the 2nd respondent - Patrick Chen; M/s. Allen & Gledhill

JUDGMENT

Salleh Abas LP:

In this case the appellants/plaintiffs sued Public Bank Berhad, the first respondent, for an injunction to restrain it from paying Sedaya Sdn. Bhd., the 2nd respondent, a certain sum of money due from the appellant to the 2nd respondent on the ground that a greater sum was due from the 2nd respondent to the appellant. Both sums arose out of a sale and purchase agreement of a house, the first sum being the balance of the purchase price whilst the second was an amount of liquidated damages for late delivery of vacant possession. The Court below refused to issue the injunction requested for.

The facts of this case are set out in the affidavit of the appellants sworn on 8 May 1987. These are as follows:

The appellants purchased a two-storey link house which was to be constructed by the 2nd respondent for RM145,000. For this purpose the appellants and the 2nd respondent entered into a sale and purchase agreement on 18 August 1982 by paying a booking fee of RM1,000 subject to various payments including progress payments. According to Clause 18 of the sale and purchase agreement, which was only signed on 18 March 1983, the building was to be so constructed that the 2nd respondent had to give vacant possession within 24 months of the date of the agreement i.e. 24 months from the date of payment of the booking fee (18 August 1982). This means that by 17 August, 1984, vacant possession should have been handed over to the appellants, but on that date the building was still uncompleted and no such delivery has taken place. Under the same clause the vendor has to pay liquidated damages at the rate of 10% per annum and these damages had been calculated to amount RM36,309.58 as at 17 February 1987. Under the same clause and 2nd respondent "shall pay immediately to the purchaser liquidated damages to be calculated from day to day at the rate of 10% per annum of the purchase price." It is therefore clear that the payment of liquidated damages is due every day from 17 February 1987.

To finance the project the appellants obtained a loan of RM100,000 from the 1st respondent and assigned the benefits under the sale and purchase agreement to the respondent as security for the loan, because no separate title has yet been issued. The property purchased is still a building lot under an approved layout plan. After taking the assignment the 1st respondent gave an undertaking to the vendor, i.e. the 2nd respondent that it would pay any monies due under the sale and purchase agreement. The amount of such money being due in this case is RM29,000, of which RM21,750 is to be paid upon the delivery of vacant possession; the remainder, being the retention amount, has to be paid as follows: i.e. RM3,625 at the expiry of six months and another RM3,625 at the expiry of twelve months, after the handing over of vacant possession.

It is the contention of the appellants that, since the liquidated damages which the 2nd respondent has to pay to them exceeds the amount of balance of the purchase price for the house payable by them to the 2nd respondent, they are no longer bound to pay any money to the 2nd respondent but instead entitled to the difference. Thus they sued the 1st respondent for an injunction to prevent the 1st respondent from paying the balance in the purchase price over to the 2nd respondent.

The 1st respondent on the other hand said that they cannot agree to the injunction or to the request of the appellants because it would mean that they will be committing a breach of their undertaking which they have given to the 2nd respondent. But the appellants contended that the 1st respondent's undertaking was not a valid undertaking.

In our view this matter could be resolved by looking at the deed of assignment executed between the appellants and the 1st respondent on 7 November 1983. This deed is a very long one, mostly dealing with the rights and obligations regarding the payment of the loan and the management of the property between

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top