2006 MarsdenLR 2501

HIGH COURT (MELAKA)

LOW HOP BING, J


MALAYSIA BUILDING SOCIETY
versus
MODERN CREST SDN BHD

GUAMAN NO: 22-99 TAHUN 1999

Decided On : 11-28-06

Advocates:
Counsel for Plaintiff - Abu Bakar Jais,Helmi Hamzah,; M/s Hisham, Sobri & Kadir
Counsel for Defendant - T Y Teh,; M/s T Y Teh & Partners

JUDGMENT

I. PLAINTIFF'S CLAIM

This is the plaintiffs claim against all the three defendants for the sum of RM52,905,900.58 as at 27 November 1998, with interest thereafter at 12% p.a. until the date of realisation, and costs.

The writ has been served on the second and third defendants on the same date i.e. 18 October 1999. As these two defendants had failed to enter appearance, judgment in default thereof in the above terms had been entered against them on 8 December 2000.

The first defendant filed its defence on 4 October 2000. I am therefore concerned only with the hearing and determination of the plaintiffs claim against the first defendant.

II. FACTS OF THE CASE

Parties herein have agreed not to call any witness, but to rely on the bundle of documents and witness' statements from which the relevant facts may be set out as follows:-

The first defendant has vide a proposal paper and letter of application dated 2 April 1996 applied to the plaintiff for a term loan of RM5 5 million and a bridging loan of RM 18 million to partly finance the development of Kota Melaka 2 and Melaka Inland Port (collectively, "the project") on an approximately 646.7 acres of land situated in Simpang Empat Melaka ("the project land").

Pursuant to the plaintiffs letter of offer dated 24 July 1996, the plaintiff agreed to grant loan facilities to the defendant for a total sum of RM77 million, of which RM42 million was by way of term loan and RMS5 million as bridging loan, both with interest at 11% p.a. on monthly rests, subject to the plaintiffs right to vary it by way of written notice to the first defendant, and, for late payment, an additional interest of 1% p.a. above the prescribed rate.

The first defendant vide letter dated 26 July 1996 accepted all these terms which were further confirmed by the first defendant vide letter dated 29 July 1996. On 14 August 1996, the plaintiff and first defendant entered into a loan agreement, wherein para 4 (a) provides for the term loan to be divided into two parts viz RM30 million to redeem the project land and RM12 million to partly finance the development deposit for the project.

A reference hereinafter to a paragraph is a reference to that paragraph in the loan agreement, unless the context otherwise requires.

Para 4(b) divides the bridging loan into three parts viz RMS million to finance the pre-development of the project, RM18 million to finance part of the costs in the development of industrial park and RM12 million to finance part of the costs in the development of inland port.

For the above facilities, the first defendant provided the following securities:-

(1) a third party legal charge dated 14 August 1996 executed by Medan Kartika Sdn Bhd;

(2) a debenture dated 10 October 1996 executed by the plaintiff; and

(3) a deed of guarantee and indemnity dated 14 August 1996 executed by the second and third defendants.

The plaintiff had on 20 August 1996 and 26 August 1996 disbursed a total sum of RM38 million to the first defendant.

Pursuant to para 20, the plaintiff also imposed on the first defendant a sum of RM28,000 by way of professional fees.

The plaintiff had delivered to the first defendant monthly statements of account.

The plaintiffs former solicitors had vide letter dated 28 February 1997 demanded payment by the first defendant of the outstanding sum of RM40,275,437.27 within seven days thereof, failing which the plaintiff would resort to litigation.

Vide letter dated 7 March 1997 to the plaintiff, the first defendant confirmed that it would settle the interest of RM2,275,437.27. The plaintiff has from 1 September 1997 to 1 September 1999 by eight written notices to the first defendant varied the original rate of interest at 11% p.a.

In view of the default and breach of the loan agreement by the first defendant, plaintiff has vide letter dated 30 December 1997 terminated the loan agreement and subsequently filed the claim herein.

III. UNPLEADED ISSUE

First defendant's learned counsel Mr. T.Y. Te

1
2
3
4
5
6
7
8
9
10
11