Subject
Contract Law - Construction Contracts
Headnote
(B) Contracts - Privity of contract - The defendants contended there was no privity of contract between them and the plaintiff, establishing that any payments made were on behalf of the main contractor. The court found evidence of a direct payment arrangement indicating a contractual nexus. (Paras 3, 10, 12)
(C) Final certificate - The absence of a final certificate does not bar recovery of claims as long as valid grounds exist, reflecting the reality of work completed; thus, claims can be considered despite non-issuance. (Paras 19, 20)
(D) Quantum of claims - The court evaluated claims for loss and expense based on established facts, allowing claims for variations, retention sums, and other validated expenses while rejecting claims not sufficiently substantiated. The proper approach is in line with the principles governing direct loss and expenses under contractual agreements. (Paras 22, 39)
| Table of Content |
|---|
| 1. claims for loss and expenses detailed. (Para 22 , 23 , 24) |
[22] In respect of Phase 3A and 3B it was PW3 the QS who prepared the report on the claims submitted by the plaintiff as in B2a 11-20 dated 9 April 2004 and B3a 49-56 dated 29 April 2004. PW3 stated his assessment for P's claims in Phase 3A was at B2a 17 and for Phase 3B at B3a 56. He was not crossexamined on the basis of assessment. The various heads of claim in Phase 3A are pursuant to the provisions of the subcontract between Perangsang and the plaintiff dated 23 July 2001 (B1 67-88) which adopted PAM form of contract. The various heads of claim in Phase 3B are pursuant to the letter of award dated 19 February 2001 (B1 89) where it was not disputed parties agreed to adopt PAM form of contract.
(a) Phase 3A
[23] The plaintiff's claim is for loss and expense, variation orders (VO) and retention sum.
[24] PW4 the architect confirmed the retention sum as in certificate no 41 (B1 217) to be RM815,400.39. It was put to him in cross-examination certificate no 41 was not approved and certified to which he disagreed and that it had been endorsed. The retention sum can be released to the plaintiff. The claim for VOs are supported by the architects instructions and the relevant attachments in B2a 213, 237, 296, 322, 331, 363, 365, 373, 382, 399 and 400 and amount to RM2,603,257.21. There was no challenge to this evidence and as per Lum Sow Kuen (supra) and Soon Peng Yam (supra) the failure to cross-examine a witness on important aspects of his evidence must be treated as acceptance of that part of the evidence. The claim for loss and expense is broken up into preliminaries due to extension of time (EOT), office overheads due to prolongation costs, overdraft interest and adjustment of fluctuation on labour and materials due to EOT. This is explained by PW1 in paras 24-28 of P1. Again this part of the evidence on the loss other than that pertaining to EOT no 4 was not challenged and deemed accepted.