COURT OF APPEAL KUALA LUMPUR
TEO HOCK GUAN & ANOR – Appellant
Versus
JOHORE BUILDERS & INVESTMENTS SDN BHD – Respondent
[Civil Appeal No: J-02-213 Of 1994]
[1] The appellants before us were the defendants in the Court below. The respondent was the plaintiff. We will, for convenience, refer to them throughout this judgment as plaintiff and defendants.
[2] On 8 October 1994, the High Court at Johor Bahru entered judgment in the plaintiff's favour for the sum RM804,800 together with interest and costs. The defendants had, in the action brought by the plaintiff, delivered a defence and counterclaim. The learned Judge who tried the action entered judgment on the counterclaim for a sum of RM63,375. This appeal is directed only against so much of the learned Judge's judgment as found for the plaintiff. There is no cross-appeal by the plaintiff against the award made on the counterclaim.
[3] Before dealing with the facts as are relevant to the appeal, there is one matter we may dispose of quite shortly.
[4] At the commencement of the appeal, the defendants moved this Court for leave to adduce further evidence on the issue of the capacity in which the defendants had been sued. This is the way which Counsel put it. The statement of claim alleged that the defendants were trading as a firm. That may have been true when the action was commenced. But there was no plea that the defendants were partners at all material times. In truth they had been sued in their individual capacity. It was now proposed to adduce evidence to show that the defendants were not partners when the alleged liability accrued. So much for the argument.
[5] We refused leave to adduce further evidence on two main grounds. First, nowhere in their defence did the defendants plead the fact that they were merely partners of the firm at the date of the action but not when the liability accrued. Had they done so, it would have become necessary for the trial Judge to determine that issue. But nothing of the sort was ever done. The issue was one which never arose for determination. The fresh evidence was therefore being sought to be put in on a matter that had not arisen in the Court below. It was therefore entirely irrelevant, and, for that reason, inadmissible.
[6] Second, Counsel for the defendants before us frankly conceded that the evidence in question was available at the trial. Yet it was not put in. It follows therefore that one of the vital conditions upon which is dependent the exercise of discretion by an appellate Court to permit fresh evidence was absent. (See, Lau Foo Sun v. Government of Malaysia [1970] 2 MLJ 70). The evidence, even if relevant (which is not the case), was not, on the basis of the exercise of discretionary power, admissible.
[7] With that we now turn to consider the background of the factual matrix against which this appeal arose. This has been dealt with at length and with great care by the learned Judge. We therefore find it quite sufficient for this purpose to extract the relevant passages from his judgment.
The plaintiffs' claim against the defendants is for a sum of RM2,461,750 being liquidated damages for the delay in completing 90 units of dwelling houses.
The plaintiffs alleged that by a written agreement dated 11 August 1981, the defendants contracted with the plaintiffs to provide labour for masonary, carpentry and steel bending for the construction of 90 units of dwelling houses to be erected on Taman Sri Setia in Johore Bahru. The 90 units of houses were to be completed within 10 months from date of the agreement, which was 11 June 1982. According to the plaintiffs, the defendants failed to do so, and under cl 27 of the agreement, is entitled to liquidated damages of RM50 per day per house. To support this claim for, RM2,461,750, the plaintiffs based their calculation on the completion of the said house according to a chart, tendered in evidence as P6.
The defendants' defence asserted that they have completed 46 units on the 31 January 1983 and 44 units on the 31 March 1983. Further they alleged that the plaintiffs had breached the agreement by inter alia:
(a) failing t
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.