SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2000 MarsdenLR 907

CHONG SIEW FAI, MOHAMED DZAIDDIN, ABDUL MALEK AHMAD
GOVERNMENT OF MALAYSIA – Appellant
Versus
SOUTH EAST ASIA INSURANCE BHD – Respondent



Advocates:
Chan Seong Gnoh (Senior Federal Counsel, Ministry of Agriculture) for the appellant.
M Pathmanathan ( Yusof Khan & Pathmanathan) for the respondent.

The court establishes that performance bonds and insurance guarantees are unconditional or on demand bonds, requiring demands for payment without proof of breach for liability.

Headnote:This judgment addresses the interpretation of a performance bond and an insurance guarantee provided by the respondent to the appellant for contract performance. The court found both documents are unconditional or on demand bonds, interpreting the necessity of proof of breach versus mere assertion in claims. The final ruling determines both documents require a written demand for payment without necessitating proof of damages, governing the amounts owed to the appellant based on contractual obligations.

Table of Content
1. facts surrounding the contractual obligations and performance bonds. (Para 1 , 2 , 3 , 4)
JUDGMENTBY: MOHAMED DZAIDDIN FCJ

(delivering judgment of the court): This appeal concerns the interpretation of a performance bond (Gerenti Perlaksanaan) and an insurance guarantee both dated 16 May 1991 given by the respondent to the appellant for the due performance of contract works by Jasib Shipyard & Engineering (M) Sdn Bhd (the contractor) under a contract no PPS 13/90 dated 25 January 1992 (the said contract).

Leave was granted by this court on 4 August 1998 to determine whether the said performance bond and the insurance guarantee are conditional or on demand bonds.

Background

Briefly, the facts are as follows. On 25 January 1992 the contractor entered into the said contract with the appellant to construct and complete the partially completed beach restoration works between Sungai Terengganu and Kuala Ibai, Kuala Terengganu. In consideration of the due performance of the said contract the respondent gave the appellant Gerenti Perlaksanaan (performance bond) for RM420,645 and an insurance guarantee against advance payment for RM1,069,035.

Sometime in November 1992, the appellant discovered that the contractor had defaulted in the completion of the works. Hence, by AR registered letter dated 30 November 1992 the appellant terminated the said contract with a copy sent to the respondent. Consequently, on 12 December 1992, the appellant sent a notice to the respondent demanding payment of RM420,645 under the Gerenti Perlaksanaan and RM1,069,035 under the Insurance Guarantee. Since the respondent failed to respond to the above demand, the appellant instituted civil action against the respondent for payment of the aforesaid sum. This was followed by an application for summary judgment under O 14 of the Rules of the High Court 1980.

At the High Court level, the registrar dismissed the application, but on appeal, the learned High Court judge reversed the registrars decision and gave summary judgment against the respondent. On further appeal, the Court of Appeal on 24 September 1996 found that there were triable issues in the case and allowed the respondents appeal, set aside the learned judges decision and restored the decision of the learned registrar.

The issue here and in the Court of Appeal is on the construction of the Gerenti Perlaksanaan and the Insurance Guarantee against advance payment. With respect to the Gerenti Perlaksanaan, paras 1 and 2 provide:

(1) Jika kontraktor (melainkan ... layak) mungkir melaksanakan

kontrak mengenai apa-apa perkara atau melakukan apa-apa

perlanggaran terhadap kewajipannya di bawah kontrak, maka

Kerajaan akan, jika perlu, memberi penggerenti peluang untuk

berbincang sebelum sesuatu keputusan dibuat.

(2) Penggerenti akan membayar gantirugi kepada Kerajaan sebanyak dan

setakat RM420,645 dalam tempoh tiga bulan selepas menerima satu

notis bertulis mengkehendaki penggerenti membayar kepada Kerajaan

apa-apa perlanggaran oleh kontraktor terhadap kewajipannya di

bawah kontrak dengan sentiasa tertakluk bahawa segala apa-apa

amaun wang bayaran oleh penggerenti tidak melebihi had yang

disebutkan dalam perenggan ini.

The Court of Appeal held there were triable issues with regard to the construction of the documents. In its judgment (at p 241 of the appeal record) the court held:

From the wordings of both the clauses above, it would appear that the

liability under cl 2 would only arise after the breach mentioned in cl

1 occurs. Therefore the question as to whether the performance bond is

a conditional one or an on demand one becomes an issue and there ought

to be a trial to determine this which in turn will affect the validity

of the notice issued by the respondent.

It concluded (at p 242):

We are satisfied that the bond

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top