SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 260

COURT OF APPEAL PUTRAJAYA
SUNWAY CITY SDN BHD – Appellant
Versus
OTIS ELEVATOR COMPANY (M) SDN BHD & ANOTHER APPEAL – Respondent
[Civil Appeal Nos: B-02(NCvC)(W)-10-01/2024 & B-02(NCvC)(W)-31-01/2024]



Petitioner Advocates:Harold Tan Kok Leng,Damia Amani Shaiful Bahri ,Respondent Advocate: Deepak Mahadevan,Loon Ann Ni

The court affirmed that a party's contractual obligations are fulfilled by issuing demand letters, and claims for unjust enrichment are unsustainable if no benefit was received by the defendant.

Headnote:(A) Contract Law - Agreement for Payment - Limitation Act 1953 - Dispute regarding repayment of disbursed sums under a construction contract - The court found that Otis had fulfilled its obligations under the Agreement for Payment by issuing letters of demand, but was not required to initiate legal proceedings due to the statutory limitation period having expired. (Paras 33, 39, 42, 75)

(B) Unjust Enrichment - The court ruled that Otis's claim for unjust enrichment against SPYTL was unsustainable as SPYTL did not receive any benefit from the payments made by Sunway to Otis, which were made under a separate agreement. (Paras 58, 64, 75)

Facts of the case:
Sunway City Sdn Bhd appealed against the dismissal of its claim for repayment from Otis Elevator Company, which in turn appealed against the dismissal of its third-party claim against Syarikat Pembenaan Yeoh Tiong Lai for contribution and indemnity. The disputes arose from a construction project and related contracts. (Paras 2-4, 28-29)

Findings of Court:
The court upheld the High Court's findings that Otis had complied with its obligations under the Agreement for Payment and that its claims against SPYTL were time-barred. The court also affirmed that SPYTL was not unjustly enriched as it did not benefit from the payments made by Sunway to Otis. (Paras 38, 75, 79)

Issues: The main issues included whether Otis had fulfilled its contractual obligations under the Agreement for Payment and whether Otis's claim for unjust enrichment against SPYTL was valid. (Paras 31, 58)

Ratio Decidendi: The court reasoned that Otis's obligations were fulfilled by issuing letters of demand and that the statutory limitation period for claims had expired, precluding further legal action. The claim for unjust enrichment was dismissed as SPYTL did not receive any benefit from the payments made by Sunway. (Paras 33, 58, 75)

Result: Appeals dismissed with costs. (Para 79)

Table of Content
1. appeals are interconnected. (Para 1 , 2 , 3 , 4)
2. factual background and contractual relationships. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27)
3. sunway's contention on otis's obligations. (Para 28 , 29 , 30 , 31)
4. court's interpretation of contractual obligations. (Para 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46)
5. otis's arguments on unjust enrichment. (Para 49 , 51 , 52 , 53 , 54 , 55 , 56)
6. court's findings on unjust enrichment and limitations. (Para 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 71 , 72 , 73 , 74)
7. final ruling on appeals. (Para 77 , 78 , 79)
JUDGMENT

Alwi Abdul Wahab JCA:

Preliminaries

[1] The appeals in R7 and R8 are related and were heard together on 25 February 2025 as they were arising from the same decision of the learned High Court Judge given on 7 December 2023.

[2] In respect of R7 (Appeal 10), it was an appeal by Sunway City Sdn Bhd ("Sunway") on the dismissal of its claim against Otis Elevator Company (M) Sdn Bhd ("Otis") for the return of the disbursed sum paid by Sunway to Otis pursuant to Agreement for Payment and the Letter of Undertaking executed between them.

[3] In respect of R8 (Appeal 31), it was an appeal by Otis on the dismissal of its claim (third party proceeding) against Syarikat Pembenaan Yeoh Tiong Lai ("SPYTL") for contribution and indemnity of the disburse sum payable to Sunway in the event that Sunway succeeded in its claim against Otis.

[4] It must be highlighted that the outcome of Sunway's Appeal will have a determining effect on Otis's Appeal as the determination of SPYTL's liability, if any, would only arise if this Court allows Sunway's appeal and makes a finding that Otis is liable towards Sunway's claim.

The Background Facts

[5] It would appear that the background facts are mostly not in dispute and the chronology of events can be gleaned from the documentary evidence exhibited by the respective parties. Those facts are essentially as follows.

[6] Pursuant to a Building Contract dated 2 March 2009 Sunway as employer appointed SPYTL as its main contractor to carry out and complete the construction of the project known as "Cadangan Pembangunan 2 Blok Pangsapuri 20 Tingkat (160 Unit), Tempat Letak Kereta 4 Tingkat, Kemudahan Penduduk dan Tembok Penahan Di Atas Lot 48629 (F2), Jalan Sri Hartamas 3, Mukim Kuala Lumpur, Wilayah Persekutuan" ("the Project").

[7] SPYTL in turn appointed Otis as its nominated sub-contractor for the supply, installation, testing and commissioning of lift services under the Project for the sum of RM6,845,730.00.

[8] SPYTL and Otis then executed a Sub-Contract dated 2 March 2009 based on the PAM Sub-Contract Form (Private Edition with Quantities) (1998 Edition) with amendments ("Sub-Contract").

[9] As there were disputes between Sunway and SPYTL, the Building Contract between Sunway and SPYTL was terminated on 27 September 2010 before the Project was completed leading to the parties referring their disputes for arbitration.

[10] Due to the termination of the Building Contract between Sunway and SPYTL, the Sub-Contract between SPYTL and Otis was terminated automatically pursuant to cl 21.1 of the Sub-Contract.

[11] As of the termination date, SPYTL allegedly owed Otis a total of RM2,676,903.95 for work completed on the project. This sum consisted of payments under the Interim Payment Certificates ("IPC") No 30, IPC No 32R, IPC No 33 and Revised Final Valuation of Works.

[12] Subsequent to the termination of the Sub-Contract between SPYTL and Otis, and unknown to SPYTL, Sunway agreed to pay Otis this amount of RM2,676,903.95 under a Letter of Undertaking (issued by Otis dated 26 January 2011) and Agreement for Payment, which was executed on 28 January 2011 between Sunway and Otis. Sunway has fully disbursed the said sum of RM2,676,903.95 to Otis on 27 January 2011.

[13] However, the arbitration proceedings between Sunway and

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top