1976 MarsdenLR 298
FEDERAL COURT, KUALA LUMPUR
BEE CHUAN RUBBER FACTORY SDN BHD – Appellant
Versus
LOO SAM MOI – Respondent
[Civil Appeal No. 125 Of 1975]
JUDGMENT
Gill CJ (delivering the JUDGMENT of the Court):
This was an appeal by the defendants in the action from the judgment of Wan Suleiman FJ sitting as a High Court Judge, and there was a cross-appeal by the respondent, plaintiff in the action.
The action arose out of an agreement in writing whereby the defendants agreed to sell to the plaintiff a piece of land in Seremban for $4,000 and to build for her a house thereon for the price of $12,500.
As provided in the agreement, the plaintiff paid $3,000 on the date of the agreement. As to the balance of the purchase price for the land and the house, the defendants undertook to obtain for the plaintiff a loan of $10,500 from the Malaya Borneo Building Society, Kuala Lumpur, and the plaintiff was to pay the remaining $3,000 by two instalments of $1,500 each, the first to be paid when the foundation for the construction of the house was made and the second when the house reached roof level.
It was also agreed between the parties that upon the title to the land being issued by the appropriate authority, the defendants would execute a transfer of the land in favour of the plaintiff who would then execute a charge over the land in favour of the society and authorise the society to pay the loan amount to the defendants. The plaintiff created a charge in favour of the society on 23 June 1969 and authorised the payment of the amount of the loan to the defendants.
By mutual agreement between the parties the method of payment by the plaintiff of the sum of $3,000 by instalments was varied. The result of the variation was that the plaintiff paid $500 on 2 December 1968, $500 on 19 December 1968, $500 on 13 January 1969, $1,000 on 24 April 1969 and $500 on 4 August 1969.
By cl 5 of the agreement, it was expressly agreed that the house shall be completed and certified fit for occupation and possession by the plaintiff on 15 June 1968. Clause 12 of the agreement stipulated that time shall be of the essence of the contract. By a letter dated 24 December 1968 which was more than six months after the agreed date of the handing over of the completed house to her, the plaintiff asked the defendants to make what she called a minor amendment to the building plan of the house. The amended plan was approved only on 6 May 1969.
The building reached roof level in April 1969 by which time, as stated earlier, the plaintiff had paid only $1,500 so that there was still a balance of $1,500 to be paid. When asked to pay this sum she asked for time, and, as I have stand earlier, this sum was paid by two instalments of $1,000 and $500 on 24 April 1969 and on 4 August 1969 respectively.
Although the house was completed soon after April 1969 the certificate of fitness was not issued until 23 March 1973. The delay for the obtaining of the fitness certificate arose because of the defendants' dispute with the Public Works Department over their contribution towards the cost of connecting the water supply to the housing estate in which the house for the plaintiff was situated.
The plaintiff issued her writ in the action on 6 November 1970 claiming specific performance of the agreement and damages at the rate of $100 per month from the agreed date of completion of the house until possession of the house was given to her, being the amount of rent which she had to pay for her living accommodation elsewhere. She also claimed interest at 6% per annum on the deposit sum of $3,000 from 16 June 1968 to the date when the defendants were in a position to put her into occupation of the house, as provided in cl 6 of the agreement.
In their statement of defence the defendants stated as follows. The construction of the house under the terms of the agreement was subject to the approval of the Town Council and the original plan was not approved until 19 November 1968. The date of completion in the agreement was a mistake and should have read 15 June 1969. They were unable to build the house because of the plaintiff's request for amendment to